Project Lynx BESS
125.3 MW storage in Nueces, TX · In queue since March 2023 · Proposed COD May 2026
125.3 MW
Capacity
1
Components
Battery
3y 4m
In Queue
IA Executed
IA Phase
Signed Apr 2024
Queue → IA
1y 1m
IA → COD
2y 1m
Total Duration
1y 1m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-05-01
Project Lynx BESS is a proposed 125.36 MW battery storage project located in Nueces County, Texas. The developer is Corpus Battery Storage, LLC. The project consists of a single 125.36 MW battery component.
The project is in the ERCOT interconnection queue as entry ERCOT-25INR0329, with a queue entry date of March 8, 2023, and a proposed commercial operation date of May 1, 2026. The interconnection agreement has been executed as of April 9, 2024. The point of interconnection is the 138KV Tap 8921 Terra Verde - 8518 Kingsville.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Nueces
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Corpus Battery Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138KV Tap 8921 Terra Verde - 8518 Kingsville
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.