Northington Solar
129.81 MW generation in Wharton, TX · In queue since February 2023 · Proposed COD March 2028
129.81 MW
Capacity
1
Components
Solar
3y 9m
In Queue
IA Executed
IA Phase
Signed Oct 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 8m
IA → COD
3y 5m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2028-03-14
Projected COD moved
4 times
Dec 2025 → Mar 2028
Net change
+27 months
first report to latest
Capacity
130 → 126 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Standard Generation Interconnection Agreement executed with AEP Texas Inc
interconnection.fyiProposed completion date updated from March 2026 to December 30, 2026
interconnectionfyi.substack.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- interconnection.fyi/project/ercot-25inr0319
- cleanview.co/power-projects/planned/solar-farms/texas/25INR0319/northington-solar
- ercot.com/files/docs/2024/12/06/Capacity%20Changes%20by%20Fuel%20Type%20Charts_November_2024.xlsx
- interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&ItemMatch=Equal&DocumentType=ALL&SortBy=FilingParty&SortOrder=Descending&Page=2
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-7d3
Commercial operation date: LBNL proposed COD is 2027-07-15, but ERCOT's November 2024 capacity chart lists the project with a 2026 completion date, and Interconnection.fyi reported a change from March 2026 to December 30, 2026 in early January 2025. The ERCOT filing is more current than the LBNL queue snapshot.
Developer: No parent company or operating entity distinct from the LBNL filing entity was identified in search results. All sources reference only 'Northington Solar, LLC' or 'Northington Solar LLC' as the developer.
Status: LBNL shows IA executed on 2024-10-02 and status as active. ERCOT capacity charts from November 2024 and PUC Texas filings confirm ongoing interconnection agreement processing with AEP Texas Inc.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Northington Solar is a proposed solar generation project located in Wharton County, Texas, with a total capacity of 129.81 MW. The project is being developed by Northington Solar, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0319, with a queue entry date of February 20, 2023, and a proposed commercial operation date of July 15, 2027.
The project's Interconnection Agreement (IA) has been executed as of October 2, 2024. The point of interconnection (POI) is on the 138 kV El Campo (#8102) - Pulsar (#8192) Line, managed by AEP. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Northington Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
The 138 kV El Campo (#8102) - Pulsar (#8192) Line; AEP.
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.