Flying Kite Solar
80.38 MW hybrid in Zavala, TX · In queue since April 2023 · Proposed COD December 2027
80.38 MW
Capacity
1
Components
Solar
3y 1m
In Queue
IA Executed
IA Phase
Signed Oct 2024
Queue → IA
1y 6m
IA → COD
3y 2m
Total Duration
1y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-30
The XE Flying Kite Solar project is a proposed 80.38 MW solar generation facility in Zavala County, Texas. The project, being developed by FLYING KITE SOLAR LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0304, with a queue entry date of April 7, 2023. The proposed commercial operation date is December 30, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is planned to tap the 69kV La Pryor (#8672) - Uvalde (#8231) Line, managed by AEP. The project has appeared in recent news.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Zavala
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
FLYING KITE SOLAR LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap the 138 kV La Pryor (#8008) - Poblano (#8009)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Flying Kite SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.