Van Zandt Energy Storage
256.58 MW storage in Ector, TX · In queue since June 2023 · Proposed COD May 2027
256.58 MW
Capacity
1
Components
Battery
3y 5m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-15
Projected COD moved
4 times
Apr 2025 → May 2027
Net change
+25 months
first report to latest
Capacity
252 → 256 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Research sources and reasoning (8 recorded sources)
high confidence at research time
- kltv.com/2025/04/10/van-zandt-county-gets-restraining-order-against-lithium-battery-operation/
- kltv.com/2025/06/21/van-zandt-county-sets-court-date-determine-future-restraining-order-against-battery-facility/
- kltv.com/2025/09/05/van-zandt-county-officials-discuss-current-state-battery-storage-facility-being-built/
- ketk.com/news/local-news/van-zandt-commissioners-pass-moratorium-pausing-lithium-storage/
- cbs19.tv/article/news/local/van-zandt-temporary-restraining-lithium-battery-storage-facility/501-175e8509-f0cc-4e5f-aa2e-cd9876901d66
- tylerpaper.com/2025/03/04/van-zandt-county-residents-oppose-battery-storage-project/
- heatmap.news/plus/the-fight/hotspots/texas-investigates-battery-project-over-china-fears
- dallasexpress.com/business-markets/texas-county-may-freeze-renewable-projects-over-chinese-made-battery-concerns/
Commercial operation date: LBNL proposes 2027-05-15 COD, but project is under temporary restraining order (Apr 2025) and county moratorium (Feb 2026) halting construction. No recent sources provide updated COD targets; project timeline is legally suspended.
Developer: LBNL filing entity is 'Rocky Mountain Energy Holdings, LLC' (project shell). Multiple news sources (KLTV, Tyler Morning Telegraph, Heatmap) identify the actual developer as 'Taaleri Energia', a Finland-based renewable energy company.
Status: LBNL shows 'active' queue status, but KLTV (Apr/Jun 2025) and KETK (Feb 2026) report temporary restraining order and moratorium blocking construction. Project is legally suspended despite maintaining queue position.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Van Zandt Energy Storage is a proposed 256.58 MW battery storage project in Ector County, Texas. Developed by Rocky Mountain Energy Holdings, LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-25INR0301, with a queue entry date of June 7, 2023, and a proposed commercial operation date of April 13, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project's point of interconnection is the 1027 Odessa EHV Switch 138 kV. Van Zandt Energy Storage has been the subject of recent news coverage related to regulatory matters.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ector
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rocky Mountain Energy Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1027 Odessa EHV Switch 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-19
View all articlesVan Zandt Energy Storage
Data-driven briefing on Van Zandt Energy Storage — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.