Austin Bayou Storage I
150.68 MW generation in Brazoria, TX · In queue since March 2023 · Proposed COD June 2027
150.68 MW
Capacity
1
Components
Battery
3y 8m
In Queue
IA Executed
IA Phase
Signed Feb 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 11m
IA → COD
2y 4m
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-06-01
Projected COD moved
3 times
Feb 2025 → Jun 2027
Net change
+28 months
first report to latest
Capacity
151 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Target commercial operation date per ERCOT capacity planning
ercot.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- ercotqueue.com/project/25INR0235
- renewablesinfo.org/project/ercot-25inr0235-austin-bayou-storage-i
- interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&ItemMatch=Equal&FilingParty=centerpoint&DocumentType=ALL&SortBy=FilingParty&SortOrder=Descending
- ercot.com/files/docs/2025/12/04/Capacity-Changes-by-Fuel-Type-Charts_November_2025.xlsx
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
Commercial operation date: LBNL queue snapshot shows proposed COD of 2027-06-01. No press releases, financing announcements, or developer statements found in search results to validate or contradict this date. ERCOT capacity chart (Dec 2025) confirms 2027 target year.
Developer: All sources consistently identify Austin Bayou Solar, LLC as the developer. No parent company or operating entity identified in search results. Entity appears to be the actual project developer rather than a shell LLC.
Status: LBNL shows IA executed 2025-02-14. Multiple ERCOT queue tracking sites (ercotqueue.com, renewablesinfo.org) confirm IA status with Facility Study pending. PUC Texas filings show active interconnection proceedings with CenterPoint Energy Houston Electric.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Austin Bayou Storage I is a proposed 150.68 MW battery storage project located in Brazoria County, Texas. The project, developed by Austin Bayou Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0235, with a queue entry date of March 8, 2023.
The proposed commercial operation date for Austin Bayou Storage I is June 1, 2027. Its interconnection status is currently in the Facility Study phase.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Austin Bayou Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV Savana 43180 to Seabreeze 43020 - Ckt 27
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.