Olympic BESS
222.81 MW storage in Nueces, TX · In queue since October 2022 · Proposed COD July 2027
222.81 MW
Capacity
1
Components
Battery
4y 1m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
Projected COD moved
3 times
Apr 2025 → Jul 2027
Net change
+27 months
first report to latest
Capacity
223 MW
unchanged in the reports
Latest stage
Cancelled
last listed May 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Proposed commercial operation date per ERCOT queue filing
cleanview.coResearch sources and reasoning (3 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0222/olympic-bess
- ercotqueue.com/developer/smt-olympic-bess-llc
- search.sunbiz.org/Inquiry/corporationsearch/SearchResultDetail?inquirytype=EntityName&directionType=Initial&searchNameOrder=SMTOLYMPICBESS%20L230001111890&aggregateId=flal-l23000111189-1ad2c0ee-dfa7-45fd-a113-14089d2bc789&searchTerm=SMTMPF%2C%20LLC&listNameOrder=SMTMPF%20L150001300010
Commercial operation date: LBNL queue filing shows July 2027 COD. Cleanview aggregator confirms this date. No press releases or news coverage found to validate or contradict this timeline.
Developer: Only source is the LBNL filing entity 'SMT Olympic BESS LLC', registered as a Florida LLC per Sunbiz records. No press releases, corporate announcements, or news coverage identify the parent/operating company behind this project vehicle.
Status: LBNL status is 'active' at Facility Study stage. No news coverage of this specific project exists; search results returned unrelated Fannin County projects and aggregator listings only.
About
Generated Apr 10, 2026 · Predates May 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Olympic BESS project is a proposed 222.81 MW battery storage project located in Nueces County, Texas. The developer is SMT Olympic BESS LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0222, with a queue entry date of October 18, 2022, and a proposed commercial operation date of July 1, 2027. The project's interconnection status is currently in the Facility Study phase and will connect to the AIRLINE 138 kV Substation (Bus# 8490).
The Olympic BESS project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: May 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Nueces
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
SMT Olympic BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
AIRLINE 138 kV Substation (Bus# 8490)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CR_RN
- POI Substation
- Airline Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Olympic BESS
Data-driven briefing on Olympic BESS — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.