Claxton Solar (ERCOT-25INR0204) — Project Summary

Queue ID
ERCOT-25INR0204
Capacity
150.64 MW
Technology
Solar
Status
active
Location
Hopkins, TX
Region
ERCOT
Developer
BT Claxton Solar, LLC
IA Status
IA Executed

Claxton Solar

ERCOT-25INR0204BetaActiveSolarERCOTLBNL + Live

150.64 MW generation in Hopkins, TX · In queue since September 2022 · Proposed COD September 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

150.64 MW

Capacity

1

Components

Solar

4y 2m

In Queue

IA Executed

IA Phase

Signed Jul 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 10m

IA → COD

2y 2m

Total Duration

2y 10m

Construction75%
Queue EntrySep 21, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJul 2, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-09-17

Queue history
25INR0204 · 47 monthly ERCOT reports, Nov 2022 – Sep 2026

Projected COD moved

3 times

May 2025 → Sep 2027

Net change

+28 months

first report to latest

Capacity

153 → 151 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 21, 2022
Facilities study approvedSep 17, 2026
Interconnection agreement signedJul 2, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Sep 17, 2027
From queue filing
Developer in saved assessment
BT Claxton Solar, LLC
From queue filing
Status at research time
Active
Active — IA executed July 2025, pre-construction phase with regulatory approvals pending
Financing
Not recorded

Milestones in this assessment

IA executedJul 2, 2025

Interconnection Agreement executed with ERCOT

interconnection.fyi
COD targetSep 17, 2027Latest in this assessment

Proposed commercial operation date

interconnection.fyi
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. interconnection.fyi/project/ercot-25inr0204
  2. eia.gov/electricity/monthly/xls/table_6_05.xlsx
  3. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
  4. gem.wiki/Claxton_solar_farm

Commercial operation date: LBNL queue shows proposed COD of 2027-09-17. No news sources provide alternative dates. EIA data (Result 7) confirms project status as 'Regulatory approvals pending. Not under construction' which is consistent with the LBNL timeline.

Developer: All sources consistently identify BT Claxton Solar, LLC as the developer. No parent company or operating entity is mentioned in any search results. The entity appears to be the actual developer rather than a shell LLC.

Status: LBNL shows 'active' status with IA executed on 2025-07-02. EIA data (Result 7) confirms 'Regulatory approvals pending. Not under construction.' Texas PUC filings (Result 8) show Standard Generation Interconnection Agreement filed August 2025, confirming active interconnection process.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The proposed Claxton Solar project is a 150.64 MW solar generation facility in Hopkins County, Texas. It is being developed by BT Claxton Solar, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0204, with a queue entry date of September 21, 2022, and a proposed commercial operation date of September 17, 2027.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is planned for a tap on the 345kV line between the Allen Switch (#2514) and Monticello (#1696).

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Hopkins

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BT Claxton Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV line between Allen Switch (#2514) and Monticello (#1696)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.