Triangle Ranch Bravo
200.22 MW generation in Cottle, TX · In queue since October 2022 · Proposed COD July 2028
200.22 MW
Capacity
1
Components
Wind
4y 1m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
Projected COD moved
2 times
Aug 2025 → Jul 2028
Net change
+35 months
first report to latest
Capacity
200 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue in Facility Study phase
interconnection.fyiResearch sources and reasoning (4 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-25inr0178
- cleanview.co/power-projects/planned/wind-farms/texas/25INR0178/triangle-ranch-bravo
- renewablesinfo.org/project/ercot-25inr0178-triangle-ranch-bravo
- ercotqueue.com/project/25INR0178
Commercial operation date: LBNL queue snapshot shows proposed COD of 2028-07-01. No independent news sources or press releases found to validate or contradict this date; all search results are aggregator sites echoing the LBNL filing.
Developer: LBNL filing entity is 'Triangle Ranch Wind'. No press releases, corporate announcements, or news coverage found to identify a parent company or operating entity. Name pattern suggests possible project-LLC but no evidence of a distinct parent.
Status: LBNL status is 'active' with IA status at 'Facility Study'. No news coverage or milestones found to indicate progression beyond interconnection studies.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Triangle Ranch Bravo is a proposed 200.22 MW wind generation project located in Cottle County, Texas. The project, developed by Triangle Ranch Wind, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0178, with a queue entry date of October 6, 2022. The proposed commercial operation date is July 1, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Edith Clark 345 kV substation (#60500). The project has appeared in recent news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Cottle
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Triangle Ranch Wind
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Edith Clark 345 kV (#60500)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Triangle Ranch Bravo
Data-driven briefing on Triangle Ranch Bravo — fleet, generation, financial, and news signals.
Max 4 Wind
Data tables and metrics from the InfraSure database.
FPL Energy Oliver Wind II LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Wind queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.