Concho Pearl Storage
162.4 MW generation in Concho, TX · In queue since December 2022 · Proposed COD October 2027
162.4 MW
Capacity
1
Components
Battery
3y 7m
In Queue
IA Executed
IA Phase
Signed Jul 2024
Queue → IA
1y 7m
IA → COD
3y 3m
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-10-14
The Concho Pearl Storage project is a proposed 162.4 MW battery energy storage system in Concho County, Texas. The project, developed by Concho Pearl Solar, LLC, is interconnected within the ERCOT region under queue ID ERCOT-25INR0175. It entered the interconnection queue on December 15, 2022, with a proposed commercial operation date of October 14, 2027.
The project's Interconnection Agreement (IA) has been executed as of July 22, 2024. The point of interconnection (POI) is Tap 345kV 76009 Twin Buttes - 7077 Amos Creek. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Concho
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Concho Pearl Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 76009 Twin Buttes - 7077 Amos Creek
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ANG_ALL
- POI Substation
- Twin Buttes Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.