Wolf Spring Solar (ERCOT-25INR0172) — Project Summary

Queue ID
ERCOT-25INR0172
Capacity
195.8 MW
Technology
Solar+Battery
Status
active
Location
Dickens, TX
Region
ERCOT
Developer
Wolf Spring Solar, LLC
IA Status
IA Executed

Wolf Spring Solar

ERCOT-25INR0172BetaActiveSolarBatteryERCOTLBNL + Live

195.8 MW hybrid in Dickens, TX · In queue since December 2022 · Proposed COD August 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

195.8 MW

Capacity

1

Components

Solar

3y 11m

In Queue

IA Executed

IA Phase

Signed Aug 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 8m

IA → COD

4 years

Total Duration

1y 8m

Construction75%
Queue EntryDec 7, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 14, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-08-25

Queue history
25INR0172 · 46 monthly ERCOT reports, Dec 2022 – Sep 2026

Projected COD moved

7 times

Jul 2025 → Aug 2028

Net change

+37 months

first report to latest

Capacity

198 → 196 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 7, 2022
Facilities study approvedJan 9, 2026
Interconnection agreement signedAug 14, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 21 months ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneCOD achieved · 2024-11Jacksonville Journal-Courier · 2025-02-25

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2027
Differs from queue: Aug 25, 2028
Developer in saved assessment
Wolf Spring Solar, LLC
From queue filing
Status at research time
IA Executed
IA Executed — tax abatement under consideration by Floyd County as of Sept 2024, pre-construction phase
Financing
Not recorded

Milestones in this assessment

IA executedAug 14, 2024

Standard Generation Interconnection Agreement executed between Oncor and Wolf Spring Solar, LLC

interchange.puc.texas.gov
Permit approvedSep 2024

Floyd County Commissioners Court consideration of tax abatement agreement

co.floyd.tx.us
COD target2027Latest in this assessment

ERCOT capacity planning chart lists 2027 commercial operation target

ercot.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. co.floyd.tx.us/upload/page/1781/2024/312%20Notice%20for%2009232024%20-%20Wolf%20Spring%20Solar%20LLC.pdf
  2. interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=1925
  3. ercot.com/files/docs/2024/09/06/Capacity-Changes-by-Fuel-Type-Charts_August_2024.xlsx
  4. cleanview.co/power-projects/planned/solar-farms/texas/25INR0172/wolf-spring-solar

Commercial operation date: ERCOT capacity chart (Sept 2024) lists Wolf Spring Solar with 2027 COD, one year earlier than LBNL's 2028-08-25 filing date. This reflects a more recent planning update.

Developer: No parent company or operating entity identified in search results. Floyd County tax abatement notice and PUCT filings confirm Wolf Spring Solar, LLC as the project entity with no evidence of a separate parent operator.

Status: LBNL shows IA executed Aug 2024. Floyd County tax abatement notice (Sept 2024) indicates active local permitting/incentive discussions, consistent with pre-construction development phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Wolf Spring Solar is a proposed 195.7 MW solar generation project located in Dickens County, Texas. The developer is Wolf Spring Solar, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-25INR0172, with a queue entry date of December 7, 2022, and a proposed commercial operation date of April 19, 2028. The interconnection agreement for the project was executed on August 14, 2024.

The Wolf Spring Solar project has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Dickens

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Wolf Spring Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 59904 Cotton Wood - 23922 White River Ckt 1

Data Source

LBNL + Live

DeveloperEDP RenewablesJacksonville Journal-Courier · 2025-02-25
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.