Piedra BESS
103.65 MW generation in Freestone, TX · In queue since September 2022 · Proposed COD December 2027
103.65 MW
Capacity
1
Components
Battery
4y 2m
In Queue
IA Executed
IA Phase
Signed Jul 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 10m
IA → COD
3y 5m
Total Duration
1y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-01
Projected COD moved
6 times
Jun 2025 → Dec 2027
Net change
+30 months
first report to latest
Capacity
102 → 104 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Expected commercial operation per PUC Texas generation plant tracking
ftp.puc.texas.govResearch sources and reasoning (6 recorded sources)
high confidence at research time
- interconnection.fyi/project/ercot-25inr0169
- ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
- ercot.com/files/docs/2024/12/06/Capacity%20Changes%20by%20Fuel%20Type%20Charts_November_2024.xlsx
- ercot.com/files/docs/2025/12/04/Capacity-Changes-by-Fuel-Type-Charts_November_2025.xlsx
- ercotqueue.com/project/25INR0169
- interchange.puc.texas.gov/Documents/35077_2310_1558933.PDF
Commercial operation date: LBNL queue shows 2027-05-10, but multiple ERCOT official sources (PUC Texas gentable.xls and ERCOT capacity charts from Nov 2024 and Nov 2025) consistently list Dec-26/2026 as the expected COD. The 6-month earlier date reflects updated project timeline post-IA execution in July 2024.
Developer: All sources consistently identify Piedra Solar, LLC as the developer with no evidence of shell-LLC structure or parent company. PUC filings and ERCOT documents uniformly reference Piedra Solar, LLC as the operating entity.
Status: LBNL correctly shows IA Executed (July 2024). ERCOT queue tracker confirms IA + FIS complete with 86% build-chance score, indicating advanced development stage with no withdrawal or suspension signals.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Piedra BESS project is a proposed 100.4 MW battery storage project located in Freestone County, Texas. Developed by Piedra Solar, LLC, the project is interconnected within the Electric Reliability Council of Texas (ERCOT) region. It entered the ERCOT interconnection queue as queue ID ERCOT-25INR0169 on September 2, 2022, with a proposed commercial operation date of December 31, 2026.
The project's Interconnection Agreement (IA) has been executed as of July 2, 2024. The point of interconnection is the Tap 345-kV line Navarro (68091) _x0013_ Limestone (46020). The project is currently listed as active in the interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Freestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Piedra Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345-kV line Navarro (68091) – Limestone (46020)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Simsboro Magnolia Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.