Piedra Solar
281.7 MW hybrid in Freestone, TX · In queue since September 2022 · Proposed COD January 2027
281.7 MW
Capacity
1
Components
Solar
4y 2m
In Queue
IA Executed
IA Phase
Signed Jul 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 10m
IA → COD
2y 6m
Total Duration
1y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-01-15
Projected COD moved
4 times
Jun 2025 → Jan 2027
Net change
+19 months
first report to latest
Capacity
306 → 282 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
X-ELIO and Ferrovial held groundbreaking ceremony for Piedra Solar project
newsroom.ferrovial.comProposed commercial operation date per LBNL queue
interconnection.fyiResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- newsroom.ferrovial.com/en/press-releases/ferrovial-first-stone-solar-photovoltaic-project-texas/
- eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_05
- interconnection.fyi/project/ercot-25inr0168
- corporate.totalenergies.us/discover-our-renewables-projects
Commercial operation date: LBNL proposes 2026-12-22 COD. EIA lists project as 'Under construction, less than or equal to 50 percent complete' as of their latest data. No recent news provides an updated COD target, so LBNL date stands as best available estimate.
Developer: LBNL filing entity is 'Piedra Solar, LLC' (project shell). Ferrovial press release and news extraction confirm X-ELIO as the operating developer/owner. TotalEnergies corporate site also lists Piedra Solar under their renewables portfolio, suggesting possible ownership stake or acquisition, but X-ELIO is the primary developer cited in construction-phase sources.
Status: LBNL shows IA executed 2024-07-02. Groundbreaking occurred 2023-04-27 per Ferrovial. EIA confirms project is under construction but ≤50% complete, consistent with active construction phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Piedra Solar is a proposed solar generation project located in Freestone County, Texas, with a total capacity of 300.93 MW. Developed by Piedra Solar, LLC, the project consists entirely of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-25INR0168, with a queue entry date of September 2, 2022, and a proposed commercial operation date of December 22, 2026.
The project's interconnection agreement (IA) has been executed as of July 2, 2024. The point of interconnection (POI) is the Tap 345-kV line Navarro (68091) _x0013_ Limestone (46020). The development has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Freestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Piedra Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345-kV line Navarro (68091) – Limestone (46020))
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Simsboro Magnolia Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesBattery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Piedra Solar
Data-driven briefing on Piedra Solar — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.