Nymphaea Solar
120.9 MW hybrid in Wichita, TX · In queue since September 2022 · Proposed COD July 2028
120.9 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
Projected COD moved
3 times
Dec 2025 → Jul 2028
Net change
+31 months
first report to latest
Capacity
122 → 121 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Wichita County Commissioners Court approved tax abatement incentives for the project
timesrecordnews.comExpected online June 2028 per third-party aggregator tracking ERCOT queue
cleanview.coResearch sources and reasoning (6 recorded sources)
high confidence at research time
- timesrecordnews.com/story/news/local/2025/12/09/a-move-is-underway-to-bring-another-big-solar-farm-to-wichita-county/87688404007/
- texomashomepage.com/news/wichita-county-commissioners-move-forward-with-solar-project/
- timesrecordnews.com/story/news/local/2025/02/24/massive-solar-plant-in-the-works-for-burkburnett-area/80038740007/
- cleanview.co/planned-solar-projects/TX/25INR0154/nymphaea-solar
- linkedin.com/posts/northstarcleanenergy_thank-you-to-everyone-who-joined-us-for-the-activity-7453539017285009408-E89t
- linkedin.com/posts/northstarcleanenergy_join-us-for-an-upcoming-community-open-house-activity-7445472836690862080-dhV0
Commercial operation date: LBNL proposed COD of July 2028 aligns with third-party aggregator sites citing June 2028, and no contradictory signals exist in recent news coverage from 2025-2026.
Developer: LBNL filing uses project-LLC 'Nymphaea Solar, LLC', but LinkedIn posts and community open house materials (April 2026) clearly identify NorthStar Clean Energy as the operating developer hosting public engagement.
Status: LBNL status 'active' confirmed by Dec 2025 county commissioners approval of tax abatement and April 2026 community open house hosted by NorthStar, indicating active pre-construction development.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Nymphaea Solar, a proposed solar generation project with a total capacity of 120.9 MW, is located in Wichita County, Texas. The project, developed by Nymphaea Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0154, with a queue entry date of September 21, 2022.
The proposed commercial operation date for Nymphaea Solar is July 1, 2028. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 1730 Krum West Swtich - 6111 Riley7B.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wichita
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Nymphaea Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1730 Krum West Swtich - 6111 Riley7B
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Nymphaea Solar
Data-driven briefing on Nymphaea Solar — fleet, generation, financial, and news signals.
Nymphaea Storage growth signals — PPAs, construction, new projects
Data-driven briefing on Nymphaea Solar — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.