Dolce BESS
100.65 MW storage in Mitchell, TX · In queue since September 2022 · Proposed COD January 2029
100.65 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 4m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-31
Projected COD moved
7 times
Dec 2025 → Jan 2029
Net change
+37 months
first report to latest
Capacity
101 → 101 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
- 2026-05·Samsung C&T Renewables, LLC→KOSPO partnership (with HD Hyundai Electric, Alpha Asset Management, Hunt Energy Network)asiae.co.kr
Milestones in this assessment
Mitchell County public hearing for 100MW 2-hour lithium-ion BESS facility
co.mitchell.tx.usKOSPO signs Joint Development Agreement with HD Hyundai Electric, Alpha Asset Management, Hunt Energy Network for Texas BESS project
mk.co.krProposed completion date updated from Aug 2026 to June 27, 2027
interconnectionfyi.substack.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- asiae.co.kr/en/article/2026052615561308684
- mk.co.kr/en/business/12057732
- co.mitchell.tx.us/upload/page/9644/docs/2024/20241112%20-%20Public%20Hearing.pdf
- lorenz-g.github.io/tesla-megapack-tracker/all-big-batteries.html
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-442
Commercial operation date: LBNL shows 2028-09-18, but Interconnection Weekly (Feb 2025) reports proposed completion changed to June 27, 2027. Tesla Megapack tracker also shows ~2028-04 planning window, suggesting mid-2027 to early-2028 range.
Developer: LBNL filing entity is 'Dolce BESS, LLC' (project shell). Tesla Megapack tracker identifies Samsung C&T Renewables, LLC as the actual developer. Recent Korean press (May 2026) reports Korea South Power (KOSPO) entering Texas BESS market via four-way partnership with HD Hyundai Electric, Alpha Asset Management, and Hunt Energy Network, suggesting potential ownership structure involving Samsung C&T as developer of record with KOSPO partnership.
Status: LBNL shows 'active' in Facility Study. Mitchell County public hearing notice (Nov 2024) confirms project is in planning/permitting phase. No construction announcement yet.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Dolce BESS is a proposed 100.65 MW battery storage project located in Mitchell County, Texas. The project, developed by Dolce BESS, LLC, is interconnected within the ERCOT region under queue ID ERCOT-25INR0139. The project entered the interconnection queue on September 27, 2022, and has a proposed commercial operation date of January 31, 2028. Its interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing operating Dolce BESS, LLC facility (EIA ID 67919). Recent news coverage has highlighted industry aspects of the Dolce BESS project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Mitchell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dolce BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 1189 BARBER_LK1_8 - 19520 CHINAGRVX2_8
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
- POI Substation
- China Grove Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.