SOSA Storage (ERCOT-25INR0131) — Project Summary

Queue ID
ERCOT-25INR0131
Capacity
155.3 MW
Technology
Battery
Status
active
Location
Madison, TX
Region
ERCOT
Developer
Sosa Energy Center, LLC
IA Status
IA Executed

SOSA Storage

ERCOT-25INR0131BetaActiveBatteryERCOTLBNL + Live

155.3 MW storage in Madison, TX · In queue since July 2022 · Proposed COD July 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

155.3 MW

Capacity

1

Components

Battery

4y 4m

In Queue

IA Executed

IA Phase

Signed Dec 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 5m

IA → COD

3y 7m

Total Duration

1y 5m

Construction75%
Queue EntryJul 25, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 5, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-07-20

Queue history
25INR0131 · 50 monthly ERCOT reports, Jul 2022 – Sep 2026

Projected COD moved

5 times

Sep 2025 → Jul 2027

Net change

+22 months

first report to latest

Capacity

151 → 155 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJul 25, 2022
Facilities study approvedJul 13, 2026
Interconnection agreement signedDec 5, 2023
On ERCOT's inactive listNov 2025 – Nov 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
—
Developer in saved assessment
Energy Vault Holdings, Inc.
Filed as Sosa Energy Center, LLC
Status at research time
Construction
Construction — groundbreaking occurred January 2026, part of Energy Vault's Asset Vault investment platform
Financing
Secured
Project financed under Energy Vault's Asset Vault investment platform; construction commenced Q4 2025 with company reporting $100M+ cash and positive Q4 2025 adjusted EBITDA

Milestones in this assessment

IA executedDec 5, 2023

Interconnection Agreement executed with ERCOT

dailyenergyinsider.com
GroundbreakingJan 2026

Construction began Q4 2025, officially announced January 2026 as first Asset Vault platform project

businesswire.com
COD target2027Latest in this assessment

Expected online 2027 per ERCOT filings and third-party tracking

cleanview.co
Research sources and reasoning (6 recorded sources)

high confidence at research time

  1. dailyenergyinsider.com/innovation/50755-energy-vault-starts-construction-on-battery-energy-storage-system-in-texas/
  2. pv-magazine-usa.com/2026/01/06/energy-vault-begins-construction-on-150-mw-storage-project-in-texas/
  3. enr.com/articles/62307-energy-vault-expands-its-footprint-in-the-texas-market
  4. businesswire.com/news/home/20260105513853/en/Energy-Vault-Begins-Construction-of-150-MW-SOSA-Energy-Center-in-Texas-ERCOT-Market-in-Q4-2025-Bringing-Total-Asset-Vault-Portfolio-Under-Operation-Construction-to-Over-340-MW-While-Growing-Cash-in-the-Quarter-by-65-to-Over-%24100-Million
  5. power-technology.com/news/energy-vault-sosa-energy-center/
  6. cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0131/sosa-storage

Commercial operation date: LBNL proposed COD is May 2027, but Energy Vault's official press release (Business Wire, Jan 5 2026) states construction began in Q4 2025, and multiple sources confirm groundbreaking in early January 2026. Given typical 12-18 month BESS construction timelines, late 2026 or early 2027 is more realistic than May 2027.

Developer: LBNL filing entity is 'Sosa Energy Center, LLC' (project SPV), but all press releases and construction announcements identify Energy Vault Holdings, Inc. (NYSE: NRGV) as the developer and owner. This is a standard shell-LLC vs. parent structure.

Status: LBNL shows 'Active' with IA Executed (Dec 2023), but multiple independent sources confirm construction started in Q4 2025/early January 2026 (Business Wire, pv magazine, Power Technology, ENR).

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The SOSA Storage project is a proposed 157.36 MW battery energy storage system in Madison County, Texas. Developed by SOSA Energy Center LLC, the project is currently in the ERCOT interconnection queue as entry ERCOT-25INR0131, with a queue entry date of July 25, 2022. The project's proposed commercial operation date is May 11, 2027.

The project has an executed Interconnection Agreement (IA), which was finalized on December 5, 2023. The point of interconnection (POI) is Tap 138kV 25 North Zulch - 47 Hilltop Lakes.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Madison

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Sosa Energy Center, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 25 North Zulch - 47 Hilltop Lakes

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
North Zulch Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.