Goldeneye BESS
201.6 MW storage in Bell, TX · In queue since June 2022 · Proposed COD May 2028
201.6 MW
Capacity
1
Components
Battery
4y 5m
In Queue
IA Executed
IA Phase
Signed Feb 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 8m
IA → COD
4y 3m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-05-15
Projected COD moved
6 times
Apr 2025 → May 2028
Net change
+37 months
first report to latest
Capacity
202 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Generation Interconnection Agreement between Oncor Electric Delivery Company LLC and Black Mountain Energy Storage II filed with Texas PUC
interchange.puc.texas.govResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- energy-storage.news/esvolta-acquires-300mwh-ercot-bess-from-black-mountain-energy-storage/
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0100/goldeneye-bess
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- ercotqueue.com/project/25INR0100
Commercial operation date: LBNL queue shows proposed COD of May 2028. No press releases or news articles provide an updated target date. Cleanview aggregator mirrors the LBNL date, but no developer-sourced update exists.
Developer: LBNL filing entity is 'Black Mountain Energy Storage II'. No press releases or corporate announcements found for this specific project. The esVolta acquisition article references a different 150MW/300MWh BESS from Black Mountain Energy Storage (BMES), but capacity mismatch (150MW vs 201.6MW) indicates this is a separate project.
Status: LBNL shows IA executed 2024-02-26. Texas PUC Interchange confirms Generation Interconnection Agreement filing for Goldeneye BESS with Oncor. No subsequent construction or financing announcements found in search results.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Goldeneye BESS project is a proposed 201.6 MW battery storage project located in Bell County, Texas. Developed by Black Mountain Energy Storage II, the project entered the ERCOT interconnection queue as entry ERCOT-25INR0100 on June 10, 2022. The project's proposed commercial operation date is May 15, 2028.
The interconnection agreement for the Goldeneye BESS project has been executed as of February 26, 2024. The point of interconnection is the 3423 KILLEEN Switch 138 KV. The project is currently listed as active in the interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Black Mountain Energy Storage II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3423 KILLEEN Switch 138 KV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.