Albatross BESS
50.4 MW storage in Mclennan, TX · In queue since May 2022 · Proposed COD February 2028
50.4 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Facility Study
IA Phase
COD target: 2028
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-02-22
The Albatross BESS project is a proposed 50.4 MW battery storage project located in McLennan County, Texas. Developed by Albatross Solar, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-25INR0071 on May 16, 2022. The current proposed commercial operation date is February 22, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 50.4 MW of battery storage capacity. The point of interconnection is specified as "From Bus #165 Windsor Switch To Bus #161 McGregor". The Albatross BESS project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Mclennan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Albatross Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
From Bus #165 Windsor Switch To Bus #161 McGregor
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.