Argenta Storage
192 MW generation in Bee, TX · In queue since June 2022 · Proposed COD June 2028
192 MW
Capacity
1
Components
Battery
4y 5m
In Queue
IA Executed
IA Phase
Signed Apr 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 10m
IA → COD
4y 2m
Total Duration
1y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2028-06-30
Projected COD moved
4 times
Jun 2025 → Jun 2028
Net change
+36 months
first report to latest
Capacity
162 → 192 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
ERCOT Standard Generation Interconnection Agreement executed between AEP Texas Inc. and Charter Oak Storage, LLC
interchange.puc.texas.govERCOT capacity charts show updated COD target of 2027, revised from earlier 2026 and 2028 dates
ercot.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- ercot.com/files/docs/2025/03/07/CapacityChangesbyFuelTypeCharts_February_2025.xlsx
- interconnectionfyi.substack.com/p/interconnectionfyi-weekly-digest
- ercot.com/files/docs/2026/02/05/Capacity-Changes-by-Fuel-Type-Charts_January_2026.xlsx
Commercial operation date: LBNL shows June 2028, but ERCOT's February 2025 capacity chart lists 2027 COD, and a December 2024 interconnection.fyi digest notes the proposed completion changed from June 2026 to June 2027. The 2027 date appears in multiple recent ERCOT filings.
Developer: All sources consistently identify Charter Oak Storage, LLC as the developer with no evidence of a parent company or shell structure. No press releases or corporate announcements found to suggest a different operating entity.
Status: LBNL status 'active' with IA executed April 5, 2024 is confirmed by Texas PUC filings showing the interconnection agreement with AEP Texas Inc. filed April 26, 2024. Project remains in pre-construction phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Argenta Storage project is a proposed 192 MW battery energy storage system in Bee County, Texas. Developed by Charter Oak Storage, LLC, the project is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-25INR0061 on June 27, 2022. The proposed commercial operation date is June 30, 2028.
The Argenta Storage project has an Interconnection Agreement (IA) executed on April 5, 2024. The point of interconnection is Tap 345kV 8689 Tango - 8606 Goddard. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bee
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Charter Oak Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 8689 Tango - 8606 Goddard
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.