Smith Lake Storage DC
65 MW generation in Grimes, TX · In queue since March 2022 · Proposed COD December 2028
65 MW
Capacity
1
Components
Battery
4y 4m
In Queue
Facility Study
IA Phase
COD target: 2028
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-28
Smith Lake Storage DC is a proposed 65 MW battery storage project located in Grimes County, Texas. The project, developed by Smith Lake Solar, is interconnected within the ERCOT region under queue ID ERCOT-25INR0045. It entered the interconnection queue on March 7, 2022, and has a proposed commercial operation date of December 28, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 65 MW of battery storage capacity. Its point of interconnection (POI) is at the Tap 345kV 44645 Singleton - 44900 Zenith Ckt #99. The Smith Lake Storage DC project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Grimes
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Smith Lake Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 44645 Singleton - 44900 Zenith Ckt #99
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LMO_ESR_RN
- POI Substation
- Singleton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Smith Lake Storage DCForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.