BasRanch (TEF - Due Diligence) (ERCOT-25INR0008) — Project Summary

Queue ID
ERCOT-25INR0008
Capacity
1350 MW
Technology
Gas
Status
active
Location
Ward, TX
Region
ERCOT
Developer
CPV Basin Ranch, LLC
IA Status
IA Executed

BasRanch (TEF - Due Diligence)

ERCOT-25INR0008BetaActiveGasERCOTLBNL + Live

1,350 MW generation in Ward, TX · In queue since August 2020 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

1,350 MW

Capacity

1

Components

Gas

6y 3m

In Queue

IA Executed

IA Phase

Signed Jul 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

4y 11m

IA → COD

3y 5m

Total Duration

4y 11m

Construction75%
Queue EntryAug 4, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJul 16, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2028-12-01

Queue history
25INR0008 · 60 monthly ERCOT reports, Oct 2021 – Sep 2026

Projected COD moved

2 times

Jan 2026 → Dec 2028

Net change

+35 months

first report to latest

Capacity

1350 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedAug 4, 2020
Facilities study approvedMay 5, 2025
Interconnection agreement signedJul 16, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2029
Differs from queue: Dec 1, 2028
Developer in saved assessment
Competitive Power Ventures (CPV)
Filed as CPV Basin Ranch, LLC
Status at research time
IA Executed
Active in ERCOT queue with IA executed 2025-07-16 and SS/FIS complete. A Texas Energy Fund loan agreement was announced 2025-10-30. No groundbreaking is confirmed in the sources, and COD is targeted for 2029.
Financing
Secured
Texas Energy Fund loan agreement, the fifth TxEF loan, announced 2025-10-30 by Gov. Abbott and the PUC of Texas. The loan amount is not stated in the available excerpts.

Milestones in this assessment

IA executedJul 16, 2025

Interconnection agreement executed for 1,350 MW at the tap on the 345kV Riverton Switch - Sand Lake Switch line.

app.nrgmap.com
Financing closeOct 30, 2025

Fifth Texas Energy Fund loan agreement announced for the CPV Basin Ranch 1,350 MW gas plant in Ward County.

gov.texas.gov
COD target2029Latest in this assessment

CPV expects commercial operations in 2029.

cpv.com
Research sources and reasoning (5 recorded sources)

high confidence at research time

  1. gov.texas.gov/news/post/governor-abbott-announces-texas-energy-fund-loan-to-1350-mw-west-texas-natural-gas-power-plant
  2. cpv.com/2025/10/30/cpv-basin-ranch-and-texas-energy-fund-ink-deal-for-1350-mw-ercot-project/
  3. businesswire.com/news/home/20251030191068/en/CPV-Basin-Ranch-and-Texas-Energy-Fund-Ink-Deal-for-1350-MW-ERCOT-Project
  4. app.nrgmap.com/queues/ercot-25inr0008
  5. utilitydive.com/news/texas-regulators-select-17-gas-fired-projects-10-gw-TEF-loans/725740/

Commercial operation date: The CPV press release says 'CPV Basin Ranch is expected to reach commercial operations in 2029', and the Texas Governor's TxEF announcement also says power in 2029. LBNL/ERCOT lists 2028-12-01, so the gap is about one year.

Developer: The LBNL filing entity 'CPV Basin Ranch, LLC' is the project LLC of Competitive Power Ventures. The CPV press release and the Utility Dive extraction both name CPV as the developer.

Status: LBNL shows an active queue entry with an executed IA (2025-07-16), and nrgmap shows it still active as of Sept 2026. The one aggregator listing the project as 'operational' contradicts LBNL, the news extraction, and the 2029 COD target, so it was disregarded.

Project lifecycle
as of 2024-08-30
OperationalNoUtility Dive · 2024-08-30
TechnologygasUtility Dive · 2024-08-30
DeveloperCompetitive Power VenturesUtility Dive · 2024-08-30

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The BasRanch (TEF - Due Diligence) project is a proposed 1350 MW natural gas generation facility in Ward County, Texas. Developed by CPV Basin Ranch, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0008, with a queue entry date of August 4, 2020. The proposed commercial operation date is December 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.

The proposed project consists of 1350 MW of natural gas-fired generation. The point of interconnection is a tap on the 345kV line between the Riverton Switch and the Sand Lake Switch. The BasRanch project has been the subject of recent news coverage related to regulatory matters.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Ward

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

CPV Basin Ranch, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV Riverton Switch - Sand Lake Switch

Data Source

LBNL + Live

AgencyPublic Utility Commission of TexasUtility Dive · 2024-08-30
RulingApprovalUtility Dive · 2024-08-30
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-31

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.