Cedro Hill Wind Repower
9.93 MW generation in Webb, TX · In queue since September 2023 · Proposed COD May 2026
9.93 MW
Capacity
1
Components
Wind
2y 10m
In Queue
IA Executed
IA Phase
COD target: 2026
Total Duration
2y 8m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-05-31
The Cedro Hill Wind Repower is a proposed wind generation project located in Webb County, Texas, within the ERCOT region. The project, developed by CEDRO HILL WIND LLC, has a total capacity of 9.93 MW. It consists solely of wind generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0632, with a queue entry date of September 28, 2023, and a proposed commercial operation date of April 1, 2026. The project's interconnection agreement (IA) has been executed as of September 9, 2009. The point of interconnection is the 80439 LA QUINTA 138kV.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CEDRO HILL WIND LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
80439 LA QUINTA 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- EXGNWTL_1
- POI Substation
- La Quinta Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Cedro Hill Wind RepowerForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.