Panther Creek 1 Repower
11 MW generation in Glasscock, TX · In queue since June 2023 · Proposed COD March 2026
11 MW
Capacity
1
Components
Wind
3y 1m
In Queue
Facility Study
IA Phase
COD target: 2026
Total Duration
2y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
The Panther Creek 1 Repower is a proposed 11 MW wind generation project located in Glasscock County, Texas. The developer is Panther Creek Wind Farm I&II, LLC. This project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0578, with a queue entry date of June 28, 2023, and a proposed commercial operation date of March 1, 2026. The project's interconnection status is currently in the Facility Study phase.
The Panther Creek 1 Repower development has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Glasscock
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Panther Creek Wind Farm I&II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1058 Longshore 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- PC_NORTH_1
- POI Substation
- Longshore Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Panther Creek 1 RepowerForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.