Marcus Energy Storage
201.04 MW storage in Brazoria, TX · In queue since June 2023 · Proposed COD September 2027
201.04 MW
Capacity
1
Components
Battery
3y 5m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
Projected COD moved
2 times
Sep 2025 → Sep 2027
Net change
+24 months
first report to latest
Capacity
201 MW
unchanged in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue as 24INR0570, Facility Study phase
cleanview.coResearch sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0570/marcus-energy-storage
- interconnection.fyi/project/ercot-24inr0570
- renewablesinfo.org/project/ercot-24inr0570-marcus-energy-storage
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
Commercial operation date: Only LBNL queue data provides a COD target of September 2027. No news articles or press releases found discussing this specific project's timeline or development status.
Developer: No independent sources found to verify or contradict the LBNL filing entity. Search results returned unrelated projects (Energy Vault, Prologis) and non-energy topics (Rabbi Paula Marcus, Marco Rubio). The developer appears to be a project-specific LLC with no public parent company identified.
Status: LBNL status shows 'active' with Facility Study underway as of June 2023 queue entry. No news coverage found to indicate progression beyond interconnection studies.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Marcus Energy Storage project is a proposed 201.04 MW battery storage project located in Brazoria County, Texas. Developed by Marcus Energy Storage, LLC, the project consists of 201.04 MW of battery capacity. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0570, with a queue entry date of June 7, 2023, and a proposed commercial operation date of September 1, 2027. The project's interconnection agreement status is currently in the Facility Study phase.
The proposed project's point of interconnection is Tap 138kV 39500 West Columbia Main - 110505 Sweeny Co-Gen LP Ckt 1. The Marcus Energy Storage project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Marcus Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 39500 West Columbia Main - 110505 Sweeny Co-Gen LP Ckt 1
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- NCO_RN
- POI Substation
- West Columbia Main Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.