Thomas Cameron BESS
201.52 MW storage in Lampasas, TX · In queue since June 2023 · Proposed COD April 2029
201.52 MW
Capacity
1
Components
Battery
3y 5m
In Queue
IA Executed
IA Phase
Signed Oct 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 4m
IA → COD
4y 6m
Total Duration
1y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2029-04-28
Projected COD moved
3 times
Nov 2024 → Apr 2029
Net change
+53 months
first report to latest
Capacity
201 → 206 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
- 2025-06·Enfinity Global (100%)→Enfinity Global (majority) + Daiwa Energy & Infrastructure (minority)energy-storage.news
Milestones in this assessment
Standard Generation Interconnection Agreement executed with Oncor Electric Delivery Company
interchange.puc.texas.govDaiwa Energy & Infrastructure acquires minority stake from Enfinity Global
energy-storage.newsResearch sources and reasoning (5 recorded sources)
high confidence at research time
- energy-storage.news/japans-daiwa-invests-in-enfinity-global-battery-storage-projects-in-us-europe/
- solarstoragextra.com/daiwa-acquires-enfinitys-texas-and-italy-bess-projects/
- daiwa-ei.jp/news-pdf/20240422e.pdf
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- lampasasdispatchrecord.com/news/lometa-couple-sound-alarm-over-battery-storage-plant
Commercial operation date: LBNL shows May 2027 COD, but Daiwa Energy & Infrastructure's April 2024 press release states 'Expected beginning of construction 2025' with the project 'expected to go live in 2026' per Solar Storage Extra. Multiple 2026 local news articles refer to 'the future Thomas Cameron BESS' as imminent, consistent with 2026 target.
Developer: LBNL filing entity is 'Thomas Cameron BESS LLC' (project SPV). Energy-Storage.News and Solar Storage Extra report that Daiwa Energy & Infrastructure acquired a minority stake in this project from Enfinity Global in June 2025, identifying Enfinity as the IPP/developer with Daiwa as financial partner.
Status: LBNL status is 'active' with IA executed Oct 30, 2024. Texas PUC filings confirm Standard Generation Interconnection Agreement with Oncor. Local news shows ongoing community opposition but no project cancellation.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Thomas Cameron BESS project is a proposed 201.52 MW battery storage project located in Lampasas County, Texas. Developed by Thomas Cameron BESS LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0543, with a queue entry date of June 7, 2023, and a proposed commercial operation date of May 3, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 3424 BUCKHORN SWITCH - 3422 KILLEEN SWITCH. The project has appeared in recent news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Lampasas
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Thomas Cameron BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3424 BUCKHORN SWITCH - 3422 KILLEEN SWITCH
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.