Padua Grid BESS Unit 2 (ERCOT-24INR0533) — Project Summary

Queue ID
ERCOT-24INR0533
Capacity
150.94 MW
Technology
Battery
Status
active
Location
Bexar, TX
Region
ERCOT
Developer
Padua Grid 2, LLC
IA Status
IA Executed

Padua Grid BESS Unit 2

ERCOT-24INR0533BetaActiveBatteryERCOTLBNL

150.94 MW storage in Bexar, TX · In queue since June 2023 · Proposed COD March 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

150.94 MW

Capacity

1

Components

Battery

3y 5m

In Queue

IA Executed

IA Phase

Signed Jan 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 7m

IA → COD

1y 2m

Total Duration

1y 7m

Schedule

8 months past proposed COD

Construction75%
Queue EntryJun 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJan 10, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-03-16

Queue history
24INR0533 · 36 monthly ERCOT reports, Jun 2023 – May 2026

Projected COD moved

8 times

Dec 2024 → Mar 2026

Net change

+15 months

first report to latest

Capacity

155 → 151 MW

changed in the reports

Latest stage

Commercial operation

last listed May 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJun 7, 2023
Facilities study approvedFeb 6, 2025
Interconnection agreement signedJan 10, 2025
Approved for energizationJan 21, 2026
Approved for synchronizationJan 26, 2026
Approved for commercial operationJun 2, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
2026
Developer in saved assessment
Eolian
Filed as Padua Grid 2, LLC
Status at research time
IA Executed
IA Executed (2025-01-10) — construction underway following $463M financing close in Oct 2025, targeting H1 2026 COD
Financing
Secured
$463M construction financing closed Oct 2025, led by Natixis Corporate & Investment Banking, covering Padua 2 (150MW) and Padua 3 (200MW) as a combined package

Milestones in this assessment

IA executedJan 10, 2025

Interconnection Agreement executed with ERCOT

ercot.com
Financing closeOct 9, 2025

$463M construction financing closed with Natixis for Padua 2 and Padua 3 BESS projects

prnewswire.com
COD target2026

Expected online first half of 2026 per CPS Energy capacity agreement

etn.news
constructionJan 2026Latest in this assessment

Construction underway at Padua 2 facility near San Antonio per site visit reporting

expressnews.com
Research sources and reasoning (6 recorded sources)

high confidence at research time

  1. prnewswire.com/news-releases/eolian-and-natixis-corporate--investment-banking-close-463-million-financing-for-largest-battery-energy-storage-site-in-texas-providing-needed-capacity-at-critical-location-for-the-grid-302579608.html
  2. energy-storage.news/eolian-secures-us463-million-for-1-7gwh-texas-bess-complex/
  3. expressnews.com/business/article/texas-grid-battery-storage-san-antonio-eolian-21230853.php
  4. etn.news/energy-storage/cps-energy-eolian-battery-energy-storage-projects-ercot-texas
  5. bestmag.co.uk/texas-bess-project-secures-463m-investment/
  6. ess-news.com/2025/10/10/us-energy-storage-businesses-secure-more-than-1-bn-in-flurry-of-deals/

Commercial operation date: LBNL proposed COD of 2026-03-31 aligns with multiple news sources stating 'first half of 2026' (ETN Aug 2024) and financing closed Oct 2025 for construction, supporting a 2026 timeline.

Developer: LBNL filing entity is 'Padua Grid 2, LLC' (project SPV), but all press releases, financing announcements, and capacity agreements identify Eolian as the developer and owner. PR Newswire and Energy-Storage.News consistently attribute the project to Eolian.

Status: LBNL shows IA executed Jan 2025. Financing closed Oct 2025 per PR Newswire and Energy-Storage.News, with San Antonio Express-News Jan 2026 article showing construction in progress ('currently' building the facility).

About

Saved background

Generated Apr 10, 2026 · Predates May 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Padua Grid BESS Unit 2 is a proposed 150.94 MW battery storage project in Bexar County, Texas. Developed by Padua Grid, LLC, the project consists of a single 150.94 MW battery component. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0533, with a queue entry date of June 7, 2023, and a proposed commercial operation date of March 31, 2026. The project's interconnection agreement has been executed.

The proposed project is linked to the existing Padua 2 operating plant (EIA plant ID 68913). Recent news coverage indicates that the project has been mentioned in at least four news articles, primarily related to deals.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: May 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Bexar

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Padua Grid 2, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

5395 Sommers 138kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
HIGH
Nearest Node (Estimated)
RN_PAD3_ESS

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-26

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.