Medina Lake BESS
9.8 MW storage in Bandera, TX · In queue since November 2022 · Proposed COD December 2025
9.8 MW
Capacity
1
Components
Battery
4 years
In Queue
IA Executed
IA Phase
Signed Jan 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2 months
IA → COD
2y 11m
Total Duration
2 months
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-12-20
Projected COD moved
6 times
Aug 2024 → Apr 2026
Net change
+20 months
first report to latest
Capacity
10 MW
unchanged in the reports
Latest stage
Commercial operation
last listed Mar 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Medina Lake BESS project is a proposed 9.8 MW battery storage project located in Bandera County, Texas. Developed by Regis Medina Lake LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-24INR0499. The project entered the interconnection queue on November 29, 2022, and has a proposed commercial operation date of June 14, 2025.
The project's Interconnection Agreement (IA) has been executed as of January 18, 2023.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Mar 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bandera
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Regis Medina Lake LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Station Name (TDSP Station Code) MEDILA; Load/Load Transformer Name T2; PTI BUS number 7432; Voltage in kV (Transmission Level) 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MEDILA_RN
- POI Substation
- Medina Lake Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.