Gunnar BESS
154.75 MW storage in Hidalgo, TX · In queue since February 2023 · Proposed COD November 2026
154.75 MW
Capacity
1
Components
Battery
3y 9m
In Queue
IA Executed
IA Phase
Signed Sep 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
7 months
IA → COD
3y 2m
Total Duration
7 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2026-11-25
Projected COD moved
5 times
Sep 2024 → Nov 2026
Net change
+26 months
first report to latest
Capacity
203 → 155 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
$120M financing package closed with NORD/LB and Siemens Financial Services
finance.yahoo.comExpected commercial operation date August 2026
cleanview.coResearch sources and reasoning (7 recorded sources)
high confidence at research time
- finance.yahoo.com/news/gridstor-secures-120m-gunnar-reliability-100824627.html
- renewableenergymagazine.com/storage/gridstora-announces-close-of-120-million-financing-20260309
- pulse2.com/gridstor-120-million-financing-from-nord-lb-and-siemens-for-texas-battery-energy-storage-project/
- energy-storage.news/us-roundup-over-us2-billion-of-financing-updates-from-arevon-primergy-and-gridstor/
- gridstor.com/nord-lb-siemens-financial-services-and-gridstor-announce-close-of-120-million-financing-agreement/
- power-technology.com/news/gridstor-secures-120m-gunnar-reliability-project/
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0491/gunnar-bess
Commercial operation date: LBNL proposed COD of August 2026 aligns with March 2026 financing close announcements, which indicate construction is proceeding on schedule. No contradictory dates found in recent sources.
Developer: Multiple March 2026 press releases identify GridStor as the developer and operator securing financing. 'Gunnar Reliability Project LLC' is the LBNL filing entity, a project-specific shell company.
Status: LBNL shows IA executed September 2023. March 2026 financing close from NORD/LB and Siemens Financial Services confirms project is advancing to construction phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Gunnar BESS project is a proposed 203 MW battery storage project located in Hidalgo County, Texas. Developed by BRP Blue Topaz 6, LLC, the project entered the ERCOT interconnection queue as ERCOT-24INR0491 on February 9, 2023, with a proposed commercial operation date of August 31, 2026. The interconnection agreement for the project was executed on September 22, 2023.
The Gunnar BESS project is actively listed in the ERCOT interconnection queue and has been featured in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hidalgo
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gunnar Reliability Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8029 CLOSNER4A 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SE_EDINB_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.