Forts Trail BESS 2 (ERCOT-24INR0488) — Project Summary

Queue ID
ERCOT-24INR0488
Capacity
205.54 MW
Technology
Solar+Battery
Status
active
Location
Taylor, TX
Region
ERCOT
Developer
JC Central Bluff, LLC
IA Status
Facility Study

Forts Trail BESS 2

ERCOT-24INR0488BetaActiveBatteryBatteryERCOTLBNL + Live

205.54 MW generation in Taylor, TX · In queue since February 2023 · Proposed COD March 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

205.54 MW

Capacity

1

Components

Battery

3y 9m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 1m

Facilities Study50%
Queue EntryFeb 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-02

Queue history
24INR0488 · 44 monthly ERCOT reports, Feb 2023 – Sep 2026

Projected COD moved

7 times

Dec 2024 → Mar 2029

Net change

+51 months

first report to latest

Capacity

201 → 206 MW

changed in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 20, 2023
Facilities study approvedApr 15, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jul 2027
Differs from queue: Mar 2, 2029
Developer in saved assessment
—
From queue filing
Status at research time
Active
Active — Facility Study stage, proposed COD updated to July 2027 per recent interconnection filings
Financing
Not recorded

Milestones in this assessment

COD targetJul 2027Latest in this assessment

Proposed completion date updated from June 2026 to July 2027

interconnectionfyi.substack.com
Research sources and reasoning (3 recorded sources)

medium confidence at research time

  1. interconnectionfyi.substack.com/p/interconnectionfyi-weekly-digest
  2. cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0488/forts-trail-bess-2
  3. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending

Commercial operation date: Interconnection.fyi weekly digest (Dec 2024) reports proposed completion changed from June 2026 to July 2027, which is 1 year earlier than LBNL's July 2028 date. This represents a more recent project schedule update than the LBNL queue snapshot.

Developer: Only LBNL filing entity 'JC Central Bluff, LLC' is available. No press releases, corporate announcements, or news coverage identify the parent/operating company behind this project LLC.

Status: LBNL shows 'active' status at Facility Study stage. Texas PUC filings (July 2025) and interconnection tracking confirm ongoing activity with updated timeline.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Forts Trail BESS 2 project is a proposed 201.2 MW battery storage project located in Taylor County, Texas. The developer is JC Central Bluff, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0488, with a queue entry date of February 20, 2023, and a proposed commercial operation date of July 25, 2028. The project's interconnection agreement status is currently in the Facility Study phase.

The project consists of 201.2 MW of battery storage. The point of interconnection is the 11406 Central Bluff Switch 345 kV. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Taylor

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

JC Central Bluff, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

11406 Central Bluff Switch 345 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Central

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.