Amador Storage
102.41 MW storage in Van Zandt, TX · In queue since November 2022 · Proposed COD April 2027
102.41 MW
Capacity
1
Components
Battery
4 years
In Queue
IA Executed
IA Phase
Signed Nov 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1 year
IA → COD
3y 5m
Total Duration
1 year
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2027-04-08
Projected COD moved
8 times
Dec 2024 → Apr 2027
Net change
+28 months
first report to latest
Capacity
102 → 102 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
20 residents file lawsuit seeking damages and injunction against project
energy-storage.news294th District Court Judge Chris Martin issues restraining order halting construction
ketk.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- ketk.com/news/local-news/van-zandt-county-judge-issues-restraining-order-stopping-battery-storage-facility/
- energy-storage.news/residents-in-texas-county-file-lawsuit-against-developers-over-proposed-100mw-bess-project/
- fredericksburgteaparty.org/wp-content/uploads/2025/02/Press-Release-Van-Zandt-County-Legal-Action.pdf
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0472/amador-storage
- newtools.cira.state.tx.us/upload/page/2685/2025/25-00067%20update%2007232025.pdf
Commercial operation date: LBNL proposed COD of 2026-08-07 remains the only explicit target date. No press releases or developer announcements found with alternative dates. Project appears under construction per lawsuit filings.
Developer: LBNL filing entity is 'BT Amador Storage, LLC' (project SPV). KETK news (Apr 2025) identifies the parent as 'Finnish company Taaleri Energia,' which is the renewable energy investment arm operating the project.
Status: LBNL shows 'Active' with IA executed Nov 2023. However, Van Zandt County District Court issued restraining order stopping construction (KETK Apr 10, 2025). Lawsuit filed by 20 residents seeking injunction (Energy-Storage.News Dec 23, 2024). Legal proceedings ongoing through July 2025 per court filings.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Amador Storage project is a proposed 102.58 MW battery energy storage system in Van Zandt County, Texas. The project is being developed by BT Amador Storage, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0472, with a queue entry date of November 23, 2022, and a proposed commercial operation date of May 13, 2026.
The project's Interconnection Agreement (IA) has been executed as of November 2, 2023. The point of interconnection (POI) is the 6833 Explorer Switching Station 138kV. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Van Zandt
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Amador Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6833 Explorer Switching Station 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Explorer Substation