CPS AvR CT1 Rotor Replacement
11.3 MW generation in Bexar, TX · In queue since October 2022 · Proposed COD March 2026
11.3 MW
Capacity
1
Components
Gas
3y 9m
In Queue
Facility Study
IA Phase
COD target: 2026
Total Duration
3y 5m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-28
The CPS AvR CT1 Rotor Replacement is a proposed 11.3 MW gas-fired generation project located in Bexar County, Texas. Developed by CPS Energy, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0427, with a queue entry date of October 24, 2022. The proposed commercial operation date is March 28, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The project involves a gas-fired generator with a capacity of 11.3 MW. The point of interconnection is the 5475 Braunig 345kV substation.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bexar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CPS Energy
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5475 Braunig 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BRA_AVR1_CT2
- POI Substation
- Braunig Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.