Mercury Solar III
203.5 MW hybrid in Hill, TX · In queue since August 2022 · Proposed COD April 2029
203.5 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-01
Projected COD moved
4 times
Dec 2024 → Apr 2029
Net change
+52 months
first report to latest
Capacity
204 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue as 24INR0407 in August 2022, currently in Facility Study phase
ercot.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- interconnection.fyi/projects/state/TX
- eta-publications.lbl.gov/sites/default/files/2024-09/hybrid_plant_tracking_2024_data_workbook.xlsx
- ercot.com/files/docs/2026/05/01/MORA_July2026.pdf
Commercial operation date: Only LBNL queue snapshot provides a COD target of 2029-04-01. No news or press releases found discussing project timeline or financing-backed targets. ERCOT MORA document from May 2026 confirms project remains in queue with 2029 target.
Developer: LBNL lists 'Mercury Solar' as developer. No press releases or corporate announcements found to identify parent company or confirm if this is a shell LLC. LBNL hybrid tracking workbook and ERCOT MORA both reference 'Mercury Solar' consistently.
Status: LBNL status is 'active' with IA status at 'Facility Study'. ERCOT's May 2026 MORA document lists project as active in queue with 2029 COD, confirming no withdrawal or suspension.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Mercury Solar III project is a proposed 203.5 MW solar generation facility in Hill County, Texas. The project, developed by Mercury Solar, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0407, with a queue entry date of August 16, 2022. Its proposed commercial operation date is April 1, 2029, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hill
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Mercury Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68092 Liberty Station 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Liberty Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesBattery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Mercury Solar III
Data-driven briefing on Mercury Solar III — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.