Buzios Solar
252 MW hybrid in Motley, TX · In queue since September 2022 · Proposed COD April 2026
252 MW
Capacity
1
Components
Solar
3y 10m
In Queue
IA Executed
IA Phase
Signed Nov 2023
Queue → IA
1y 2m
IA → COD
2y 5m
Total Duration
1y 2m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-04-30
The Buzios Solar project is a proposed 252 MW solar generation facility in Motley County, Texas. The project, developed by Roaring Springs Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0399, with a queue entry date of September 15, 2022. The project's proposed commercial operation date is January 30, 2026.
The interconnection agreement for Buzios Solar was executed on November 6, 2023. The point of interconnection is planned at a tap between Cottonwood (#59904) and White River (#23922). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Motley
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Roaring Springs Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap between Cottonwood (#59904) and White River (#23922)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Cottonwood Sub
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Buzios SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.