Buzios Solar (ERCOT-24INR0399) — Project Summary

Queue ID
ERCOT-24INR0399
Capacity
252 MW
Technology
Solar+Battery
Status
active
Location
Motley, TX
Region
ERCOT
Developer
Roaring Springs Solar, LLC
IA Status
IA Executed

Buzios Solar

ERCOT-24INR0399BetaActiveSolarBatteryERCOTLBNL + Live

252 MW hybrid in Motley, TX · In queue since September 2022 · Proposed COD July 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

252 MW

Capacity

1

Components

Solar

4y 2m

In Queue

IA Executed

IA Phase

Signed Nov 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 2m

IA → COD

2y 8m

Total Duration

1y 2m

Schedule

4 months past proposed COD

Construction75%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 6, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-07-31

Queue history
24INR0399 · 50 monthly ERCOT reports, Aug 2022 – Sep 2026

Projected COD moved

7 times

Aug 2024 → Jul 2026

Net change

+23 months

first report to latest

Capacity

202 → 252 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 15, 2022
Facilities study approvedMar 10, 2025
Interconnection agreement signedNov 6, 2023
Approved for energizationAug 27, 2025
Approved for synchronizationOct 1, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jun 2026
Differs from queue: Jul 31, 2026From queue filing
Developer in saved assessment
Roaring Springs Solar, LLC
From queue filing
Status at research time
IA Executed
IA Executed — project commissioned per ERCOT queue tracker, awaiting commercial operations in mid-2026
Financing
Not recorded

Milestones in this assessment

IA executedNov 6, 2023

Generation Interconnection Agreement executed between Oncor Electric Delivery Company LLC and Roaring Springs Solar, LLC

interchange.puc.texas.gov
COD targetJun 2026Latest in this assessment

Expected commercial operation date per UH Energy grid analysis

uh.edu
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
  2. uh.edu/energy/_docs/_papers-reports/the-future-of-the-electric-grid-in-texas_supplementary-material_uh.pdf
  3. ercot.com/files/docs/2025/09/02/Stand-Alone-Generation-Resources-as-of-09.01.25-v2.pdf
  4. ercotqueue.com/project/24INR0399

Commercial operation date: LBNL proposed COD of 2026-04-30 aligns with UH Energy supplementary material showing Jun-26 expected online date. ERCOT operational data from Sep 2025 shows project not yet online but progressing.

Developer: All sources consistently identify Roaring Springs Solar, LLC as the developer with no parent company or operating entity mentioned. No evidence of shell-LLC structure or ownership transfer.

Status: LBNL shows IA executed 2023-11-06, confirmed by Texas PUC filings. ERCOT queue tracker shows 'Commissioned' status with 100% build-chance, indicating advanced development stage.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Buzios Solar project is a proposed 252 MW solar generation facility in Motley County, Texas. The project, developed by Roaring Springs Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0399, with a queue entry date of September 15, 2022. The project's proposed commercial operation date is January 30, 2026.

The interconnection agreement for Buzios Solar was executed on November 6, 2023. The point of interconnection is planned at a tap between Cottonwood (#59904) and White River (#23922). The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Motley

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Roaring Springs Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap between Cottonwood (#59904) and White River (#23922)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.