PaleAle BESS (ERCOT-24INR0387) — Project Summary

Queue ID
ERCOT-24INR0387
Capacity
75.38 MW
Technology
Battery
Status
active
Location
Hays, TX
Region
ERCOT
Developer
Momentum Energy Storage Partners,LLC
IA Status
Facility Study

PaleAle BESS

ERCOT-24INR0387BetaActiveBatteryERCOTLBNL + Live

75.38 MW storage in Hays, TX · In queue since July 2022 · Proposed COD April 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

75.38 MW

Capacity

1

Components

Battery

3y 10m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

4y 9m

Facilities Study50%
Queue EntryJul 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-15

Risk Analytics

Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability
Counterparty exposure
About

The PaleAle BESS project is a proposed 75.38 MW battery storage project located in Hays County, Texas. Developed by Momentum Energy Storage Partners, LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0387, with a queue entry date of July 18, 2022, and a proposed commercial operation date of April 15, 2027. The project's interconnection status is currently in the Facility Study phase.

The point of interconnection for the PaleAle BESS project is Tap 138 kV Bus 7506 L_CEDAVA8_1Y - Bus 7507 L_FRIEND8_1Y. The project has appeared in recent news coverage regarding energy storage developments in the ERCOT region.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Hays

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Momentum Energy Storage Partners,LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138 kV Bus 7506 L_CEDAVA8_1Y - Bus 7507 L_FRIEND8_1Y

Data Source

LBNL + Live

Generation Forecast

Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year horizon (through 2034)
P10 / P50 / P90 confidence bands
Weather + policy + demand scenarios
Financial Forecast

Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year cashflow horizon
P10 / P50 / P90 DSCR bands
Price + demand + policy scenarios
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.