Remy Jade III Power Station
102 MW generation in Harris, TX · In queue since July 2022 · Proposed COD May 2028
102 MW
Capacity
1
Components
Gas
4y 4m
In Queue
IA Executed
IA Phase
Signed Aug 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1 month
IA → COD
5y 9m
Total Duration
1 month
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2028-05-01
Projected COD moved
5 times
Apr 2024 → May 2028
Net change
+49 months
first report to latest
Capacity
104 → 102 MW
changed in the reports
Latest stage
Cancelled
last listed Mar 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
- —·WattBridge→PROENERGY (Energy Capital Partners portfolio company)irei.com
- 2025-09·PROENERGY→CPS Energybizjournals.com
Milestones in this assessment
WattBridge began commercial operations at 384-MW Remy Jade facility (includes Remy Jade III unit)
prnewswire.comWattBridge withdrew four projects from Texas Energy Fund (unclear if this specific unit was affected)
latitudemedia.comCPS Energy acquired four Southeast Texas power facilities including Remy Jade for $1.3B from PROENERGY
bizjournals.comResearch sources and reasoning (6 recorded sources)
high confidence at research time
- prnewswire.com/news-releases/wattbridge-begins-commercial-operations-at-the-384-mw-remy-jade-facility-its-sixth-generating-station-in-4-years-302249578.html
- power-eng.com/news/wattbridges-sixth-texas-gas-plant-goes-online/
- wsp.com/en-us/projects/remy-jade-generating-station
- bizjournals.com/sanantonio/news/2025/09/16/cps-energy-spends-1-3b-on-south-texas-plants.html
- irei.com/news/ecp-backed-proenergy-to-sell-natural-gas-portfolio-in-texas-to-cps-energy-for-1-4b/
- latitudemedia.com/news/high-risks-costs-prompt-withdrawal-of-four-more-texas-gas-plants/
Commercial operation date: PR Newswire and Power Engineering both report WattBridge began commercial operations at the 384-MW Remy Jade facility in September 2024. LBNL's 2028-05-01 proposed COD is 3.5 years later and clearly stale. The 384 MW facility includes this 102 MW unit (Remy Jade III) as part of the larger station.
Developer: LBNL filing uses project LLC 'Remy Jade III Generating, LLC' while all press releases and news coverage identify WattBridge as the operating company that owns and operates the Remy Jade facility.
Status: LBNL status 'active' with IA executed is accurate for queue position. Facility achieved commercial operations in 2024 and was subsequently acquired by CPS Energy as part of a four-facility portfolio sale.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Remy Jade III Power Station is a proposed 102 MW gas-fired generation project located in Harris County, Texas. Developed by Remy Jade III Generating, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-24INR0382. The project entered the interconnection queue on July 18, 2022, with a proposed commercial operation date of May 1, 2028. The Interconnection Agreement (IA) for the project was executed on August 1, 2022.
The Remy Jade III Power Station has been the subject of recent news coverage, with nine articles related to the project appearing in industry and grid publications. The point of interconnection is Tap 138kV 40390 Crosby - 40811 Highlands.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Mar 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Remy Jade III Generating, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 40390 Crosby - 40811 Highlands
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CS_RN
- POI Substation
- Crosby Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.