Solara BESS 1 (ERCOT-24INR0378) — Project Summary

Queue ID
ERCOT-24INR0378
Capacity
150 MW
Technology
Battery
Status
active
Location
Jones, TX
Region
ERCOT
Developer
CED Development Inc.
IA Status
Facility Study

Solara BESS 1

ERCOT-24INR0378BetaActiveBatteryERCOTLBNL + Live

150 MW storage in Jones, TX · In queue since July 2022 · Proposed COD November 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

150 MW

Capacity

1

Components

Battery

4y 4m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 4m

Facilities Study50%
Queue EntryJul 5, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-11-30

Queue history
24INR0378 · 50 monthly ERCOT reports, Aug 2022 – Sep 2026

Projected COD moved

3 times

May 2024 → Nov 2027

Net change

+42 months

first report to latest

Capacity

150 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJul 5, 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Nov 30, 2027
From queue filing
Developer in saved assessment
CED Development Inc.
From queue filing
Status at research time
Active
Active — in Facility Study phase, no IA executed yet. Multiple tracking sources confirm project remains in queue with low build probability (5% per ercotqueue.com).
Financing
Not recorded

Milestones in this assessment

COD targetNov 30, 2027Latest in this assessment

Proposed commercial operation date per LBNL queue filing

cleanview.co
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0378/solara-bess-1
  2. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-442
  3. interconnection.fyi/project/ercot-24inr0378
  4. interconnectionfyi.substack.com/p/interconnectionfyi-weekly-digest
  5. ercotqueue.com/project/24INR0378
  6. images1.showcase.com/d2/-0De-RO-jQonkpQ2jP1NIhlV4X4KhA7CUOhUCTtJjTw/document.pdf

Commercial operation date: LBNL queue shows November 2027 COD. Interconnection.fyi reported a slip from Nov 2025 to Nov 2026 in Dec 2024, but the PDF from Nov 2025 shows 12/31/2028, suggesting continued delays. LBNL's 2027-11-30 appears to be the most recent official target.

Developer: All sources consistently identify CED Development Inc. as the developer. No evidence of shell LLC structure, ownership changes, or parent company distinctions in available sources.

Status: LBNL status 'active' with 'Facility Study' IA status is confirmed by all tracking sources. No evidence of construction activity, financing, or advancement beyond study phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Solara BESS 1 project is a proposed 150 MW battery storage project located in Jones County, Texas. Developed by CED Development Inc., the project is currently in the ERCOT interconnection queue as entry ERCOT-24INR0378, with a queue entry date of July 5, 2022. The proposed commercial operation date is November 30, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.

The project consists entirely of battery storage, with a total capacity of 150 MW. The point of interconnection is the 60387 Hendrick 138kV location. The Solara BESS 1 project has appeared in recent news coverage regarding energy storage developments in Texas.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Jones

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

CED Development Inc.

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

60387 Hendrick 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.