Glory Bee Storage (ERCOT-24INR0369) — Project Summary

Queue ID
ERCOT-24INR0369
Capacity
101 MW
Technology
Solar+Battery
Status
active
Location
Erath, TX
Region
ERCOT
Developer
Riley Solar LLC
IA Status
Facility Study

Glory Bee Storage

ERCOT-24INR0369BetaActiveBatteryBatteryERCOTLBNL

101 MW generation in Erath, TX · In queue since June 2022 · Proposed COD April 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

101 MW

Capacity

1

Components

Battery

4y 5m

In Queue

Facility Study

IA Phase

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 10m

Schedule

7 months past proposed COD

Facilities Study50%
Queue EntryJun 10, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-04-14

Queue history
24INR0369 · 45 monthly ERCOT reports, Jun 2022 – Mar 2026

Projected COD moved

2 times

May 2024 → Apr 2026

Net change

+23 months

first report to latest

Capacity

101 MW

unchanged in the reports

Latest stage

Cancelled

last listed Mar 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJun 10, 2022
Facilities study approvedApr 18, 2023
CancelledApr 20, 2026
On ERCOT's inactive listNov 2022 – Nov 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
—
Developer in saved assessment
Riley Solar LLC
From queue filing
Status at research time
Withdrawn
Withdrawn — project dropped from ERCOT queue, confirmed by multiple independent tracking sources and local community monitoring
Financing
Cancelled

Milestones in this assessment

WithdrawnApr 2026Latest in this assessment

Project cancelled and removed from ERCOT queue, listed among 43 cancelled projects in April 2026

facebook.com
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. interconnection.fyi/project/ercot-24inr0369
  2. ercotqueue.com/developer/riley-solar-llc
  3. facebook.com/groups/erathcountystopsolarfarmshere/posts/1908133659896313/
  4. interconnection.fyi/projects/state/TX/erath-county

Commercial operation date: Project has been withdrawn from ERCOT queue. Multiple sources (interconnection.fyi, ercotqueue.com, Facebook community posts) confirm 'Withdrawn' or 'Dropped' status, making the original 2026-04-14 COD no longer applicable.

Developer: Riley Solar LLC appears to be the actual developer entity with no evidence of a separate parent company. No press releases or corporate announcements found to indicate this is a shell LLC for a larger operator.

Status: LBNL shows 'active' but multiple current sources (interconnection.fyi, ercotqueue.com showing 'Dropped', Facebook posts from May 2026 listing it among cancelled projects) confirm withdrawal from queue.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Glory Bee Storage project is a proposed 101 MW battery energy storage system located in Erath County, Texas. Developed by Riley Solar LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0369, with a queue entry date of June 10, 2022. The proposed commercial operation date is April 14, 2026.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is Tap 345kV 1440 Comanche Switch - 1900 Comanche Peak. The Glory Bee Storage project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Mar 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Erath

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Riley Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 1440 Comanche Switch - 1900 Comanche Peak

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Comanche

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.