Blanket Ranch South Solar
101.3 MW hybrid in Brown, TX · In queue since June 2022 · Proposed COD September 2028
101.3 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-22
Projected COD moved
4 times
Sep 2024 → Sep 2028
Net change
+48 months
first report to latest
Capacity
137 → 101 MW
changed in the reports
Latest stage
Cancelled
last listed May 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Chapter 313 property value limitation agreement approved by Zephyr ISD, providing tax abatement for 10-year period starting 2028
zephyrisd.netProposed commercial operation date per ERCOT interconnection queue filing
interconnection.fyiResearch sources and reasoning (3 recorded sources)
medium confidence at research time
- zephyrisd.net/wp-content/uploads/2022/06/ZEPHYR-ISD-Blanket-Ranch-South-Solar-LLC-CH313-SUMMARY-5-15-2022.pdf
- cleanview.co/power-projects/developers/diode-ventures
- interconnection.fyi/project/ercot-24inr0358
Commercial operation date: LBNL queue snapshot proposes 2028-09-22 COD. No independent news sources confirm or contradict this date; the Chapter 313 tax filing from 2022 shows value limitation starting in school year 2028-29, consistent with LBNL timeline.
Developer: LBNL filing entity is 'Blanket Ranch South Solar, LLC' (project shell). Cleanview pipeline database attributes this project to Diode Ventures as the operating developer/parent company.
Status: LBNL status is 'active' at Facility Study stage. The 2022 Chapter 313 property tax limitation agreement with Zephyr ISD demonstrates the project secured local tax incentives and is progressing through development milestones.
About
Generated Apr 10, 2026 · Predates May 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Blanket Ranch South Solar SLF is a proposed solar generation project located in Brown County, Texas, within the ERCOT region. The project, developed by Blanket Ranch South Solar, LLC, has a total capacity of 134.7 MW. It consists entirely of solar photovoltaic generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0358, with a queue entry date of June 10, 2022. The proposed commercial operation date is September 22, 2028. Its interconnection status is currently in the Facility Study phase.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: May 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brown
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Blanket Ranch South Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 11441 CORN TRAIL SWITCH - 1444 BROWN SWITCH
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.