Guinness BESS
100.51 MW storage in Williamson, TX · In queue since July 2022 · Proposed COD April 2027
100.51 MW
Capacity
1
Components
Battery
4y 4m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-15
Projected COD moved
3 times
Jun 2024 → Apr 2027
Net change
+34 months
first report to latest
Capacity
100 → 101 MW
changed in the reports
Latest stage
Cancelled
last listed May 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0352/guinness-bess
- ercotqueue.com/project/24INR0352
- renewablesinfo.org/project/ercot-24inr0352-guinness-bess
- ercotqueue.com/developer/momentum-energy-storage-partners-llc
Commercial operation date: LBNL queue snapshot shows April 2027 COD. Multiple aggregator sites (Cleanview, ercotqueue.com, renewablesinfo.org) echo this date but appear to be mirroring LBNL data rather than independent sources. No press releases or news coverage found to validate or contradict.
Developer: LBNL filing entity is 'Momentum Energy Storage Partners,LLC' — appears to be the actual operating company name rather than a project-specific shell LLC. No news coverage or corporate announcements found to identify a different parent entity or confirm operational structure.
Status: LBNL shows 'active' status at Facility Study stage with no IA date. Ercotqueue.com independently confirms 'No IA' status and assigns low 5% build-chance, suggesting early-stage development with uncertain viability.
About
Generated Apr 10, 2026 · Predates May 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Guinness BESS project is a proposed 100.51 MW battery energy storage system located in Williamson County, Texas. The project is being developed by Momentum Energy Storage Partners, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0352, with a queue entry date of July 25, 2022.
The proposed commercial operation date for the Guinness BESS project is April 15, 2027. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 7520 BERTRA - 7522 ANDICE.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: May 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Williamson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Momentum Energy Storage Partners,LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 7520 BERTRA - 7522 ANDICE
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.