Eldora BESS
201.31 MW generation in Matagorda, TX · In queue since June 2022 · Proposed COD July 2028
201.31 MW
Capacity
1
Components
Battery
4y 5m
In Queue
IA Executed
IA Phase
Signed Nov 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 5m
IA → COD
4y 8m
Total Duration
1y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2028-07-02
Projected COD moved
3 times
Dec 2024 → Jul 2028
Net change
+43 months
first report to latest
Capacity
201 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Advanced Power closed $100M corporate credit facility to support 8GW development pipeline
prnewswire.comResearch sources and reasoning (6 recorded sources)
medium confidence at research time
- prnewswire.com/news-releases/advanced-power-closes-100m-corporate-credit-facility-302346522.html
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0338/eldora-bess
- cleanview.co/power-projects/developers/advanced-power
- ercotqueue.com/developer/eldora-energy-llc
- ercot.com/files/docs/2025/12/05/MORA_February2026.pdf
- ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
Commercial operation date: LBNL queue snapshot shows proposed COD of 2028-07-02, confirmed by multiple aggregator sites (Cleanview, renewablesinfo.org, ERCOT MORA report, Texas PUC table). No press releases or news articles with updated targets found.
Developer: LBNL filing entity is 'Eldora Energy LLC' (project shell). Cleanview developer profile lists Eldora BESS under Advanced Power's portfolio with 15 projects totaling 3,141 MW. PR Newswire (Jan 2025) confirms Advanced Power closed $100M credit facility to support 8GW pipeline development.
Status: LBNL shows 'active' status with IA executed 2023-11-15. Ercotqueue.com confirms 'IA + FIS complete' with 86% study progress. No construction or withdrawal announcements found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Eldora BESS is a proposed 201.31 MW battery storage project in Matagorda County, Texas. Developed by Eldora Energy LLC, the project consists of 201.31 MW of battery capacity. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0338, with a queue entry date of June 10, 2022, and a proposed commercial operation date of July 2, 2028. The project's interconnection agreement has been executed as of November 15, 2023.
The point of interconnection is the 345 kV South Texas Project (Bus# 5915) _x0013_ Hillje (Bus# 44200) Transmission Line Ckt 1. Recent news coverage indicates activity related to deals involving the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Eldora Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV South Texas Project (Bus# 5915) – Hillje (Bus# 44200) Transmission Line Ckt 1
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- South Texas Project Tap
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.