Chisme Storage (ERCOT-24INR0331) — Project Summary

Queue ID
ERCOT-24INR0331
Capacity
146 MW
Technology
Solar+Battery
Status
active
Location
Brown, TX
Region
ERCOT
Developer
Blue Heron Solar, LLC
IA Status
Facility Study

Chisme Storage

ERCOT-24INR0331BetaActiveBatteryBatteryERCOTLBNL + Live

146 MW generation in Brown, TX · In queue since January 2023 · Proposed COD April 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

146 MW

Capacity

1

Components

Battery

3y 10m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 3m

Facilities Study50%
Queue EntryJan 17, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-13

Queue history
24INR0331 · 44 monthly ERCOT reports, Jan 2023 – Sep 2026

Projected COD moved

3 times

Jul 2025 → Apr 2027

Net change

+21 months

first report to latest

Capacity

140 → 151 MW

changed in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 17, 2023
Facilities study approvedJun 23, 2026
On ERCOT's inactive listFeb 2023 – Feb 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Apr 2027
From queue filing
Developer in saved assessment
Blue Heron Solar, LLC
From queue filing
Status at research time
Active
Active — Facility Study stage, no IA executed. ERCOT May 2024 buildout report shows 'FIS Started, No IA' with 5% build-chance rating per ercotqueue.com.
Financing
Not recorded

Milestones in this assessment

IA executed

Facility Study started, no Interconnection Agreement as of May 2024

modo-content-service-prod.s3.amazonaws.com
Permit approvedDec 2024Latest in this assessment

PUC technical filing submitted specifying Sungrow inverter equipment for both Chisme Storage and co-located Chisme Solar

interchange.puc.texas.gov
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0331/chisme-storage
  2. interconnection.fyi/project/ercot-24inr0331
  3. interchange.puc.texas.gov/Documents/35077_2003_1446380.PDF
  4. modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
  5. ercotqueue.com/project/24INR0331

Commercial operation date: LBNL queue snapshot shows April 2027 COD. Multiple aggregator sites (Cleanview, interconnection.fyi, ercotqueue.com) echo this date, but no independent press releases or developer announcements found to validate or update it.

Developer: All sources consistently identify Blue Heron Solar, LLC as the developer. No parent company, operating entity, or ownership change information found in search results. Entity appears to be the actual developer rather than a shell LLC.

Status: LBNL status 'active' confirmed by multiple queue trackers. PUC filing from Dec 2024 shows technical equipment specs (Sungrow inverters), indicating ongoing engineering work. However, no IA and low build probability suggest early development stage.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Chisme Storage is a proposed 146 MW battery storage project located in Brown County, Texas. Developed by Blue Heron Solar, LLC, the project entered the ERCOT interconnection queue as ERCOT-24INR0331 on January 17, 2023. It is currently in the Facility Study phase of interconnection.

The proposed commercial operation date for Chisme Storage is April 13, 2027. The point of interconnection is Tap 345 kV 1444 BROWN SWITCH - 3424 BUCKHORN SWITCH. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Brown

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Blue Heron Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345 kV 1444 BROWN SWITCH - 3424 BUCKHORN SWITCH

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.