Backbone Creek BESS (ERCOT-24INR0313) — Project Summary

Queue ID
ERCOT-24INR0313
Capacity
124.1 MW
Technology
Battery
Status
active
Location
Burnet, TX
Region
ERCOT
Developer
Backbone Creek BESS LLC
IA Status
IA Executed

Backbone Creek BESS

ERCOT-24INR0313BetaActiveBatteryERCOTLBNL + Live

124.1 MW storage in Burnet, TX · In queue since April 2022 · Proposed COD December 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

124.1 MW

Capacity

1

Components

Battery

4y 7m

In Queue

IA Executed

IA Phase

Signed Dec 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 8m

IA → COD

3 years

Total Duration

1y 8m

Construction75%
Queue EntryApr 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 22, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-12-01

Queue history
24INR0313 · 53 monthly ERCOT reports, May 2022 – Sep 2026

Projected COD moved

6 times

Nov 2024 → Dec 2026

Net change

+25 months

first report to latest

Capacity

101 → 124 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedApr 18, 2022
Facilities study approvedSep 8, 2025
Interconnection agreement signedDec 22, 2023
Approved for energizationSep 4, 2026
Approved for synchronizationSep 21, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 2026
From queue filing
Developer in saved assessment
Backbone Creek BESS LLC
From queue filing
Status at research time
Active
Active — IA executed December 2023, targeting December 2026 COD
Financing
Not recorded

Milestones in this assessment

IA executedDec 22, 2023Latest in this assessment

Interconnection Agreement executed with ERCOT

cleanview.co
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/69167_BCKBN/backbone-creek-bess
  2. interchange.puc.texas.gov/Documents/54974_371_1552153.PDF
  3. public.destinyhosted.com/burnemindocs/2023/ComCt/20230228_4437/1416_6._Backbone_Creek_BESS_Project_Presentation.pdf
  4. interconnection.fyi/project/ercot-24inr0313

Commercial operation date: LBNL queue snapshot shows proposed COD of December 2026. No contradictory or confirming dates found in news/research sources. Cleanview aggregator confirms 'expected to come online in December' matching LBNL timeline.

Developer: All sources consistently reference 'Backbone Creek BESS LLC' as the project entity. No parent company or operating entity identified in search results. County presentation and PUC filing both list Backbone Creek BESS LLC as the legal entity.

Status: LBNL shows 'active' status with IA executed on 2023-12-22. No news of construction start, financing, or status changes found in search results. Project remains in pre-construction phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Backbone Creek BESS project is a proposed 121 MW battery storage project located in Burnet County, Texas. Developed by Backbone Creek BESS LLC, the project is interconnected within the ERCOT region and entered the ERCOT interconnection queue as ERCOT-24INR0313 on April 18, 2022. The project's proposed commercial operation date is August 10, 2026.

The project has an Interconnection Agreement (IA) executed on December 22, 2023, and its Point of Interconnection (POI) is the 7351 STARCKE 138kV substation. The project's interconnection status is currently listed as active.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Burnet

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Backbone Creek BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

7351 STARCKE 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
HIGH
Nearest Node (Estimated)
MARBFA
POI Substation
Starcke Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.