Rockridge Solar
211.2 MW generation in Guadalupe, TX · In queue since April 2022 · Proposed COD June 2028
211.2 MW
Capacity
1
Components
Solar
4y 7m
In Queue
IA Executed
IA Phase
Signed Mar 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 11m
IA → COD
3y 3m
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2028-06-27
Projected COD moved
3 times
Nov 2024 → Jun 2028
Net change
+43 months
first report to latest
Capacity
221 → 211 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Proposed commercial operation date per ERCOT capacity planning
ercot.comResearch sources and reasoning (6 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/solar-farms/texas/24INR0287/rockridge-solar
- interconnection.fyi/project/ercot-24inr0287
- ercotqueue.com/project/24INR0287
- ercot.com/files/docs/2025/12/04/Capacity-Changes-by-Fuel-Type-Charts_November_2025_PlannedMonthly.xlsx
- cleanview.co/power-projects/developers/pine-gate-renewables
- ercotqueue.com/developer/magnolia-solar-development-llc
Commercial operation date: LBNL queue snapshot shows proposed COD of 2027-04-03. No press releases, financing announcements, or developer statements found to validate or contradict this date. ERCOT public data (Result 7) confirms 2027 target year.
Developer: LBNL filing entity is 'Magnolia Solar Development LLC' (project SPV). Cleanview pipeline data (Result 8) lists Rockridge Solar under Pine Gate Renewables's development portfolio, indicating Pine Gate is the operating parent company behind the Magnolia shell LLC.
Status: LBNL shows IA executed on 2025-03-14. ERCOT queue tracker (Result 6, 12) confirms 'IA, FIS pending' status, consistent with active pre-construction phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Rockridge Solar Project is a proposed solar generation project located in Guadalupe County, Texas. Developed by Magnolia Solar Development LLC, the project has a total capacity of 221.27 MW. It consists entirely of solar photovoltaic generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0287, with a queue entry date of April 18, 2022, and a proposed commercial operation date of April 3, 2027. Its interconnection status is currently in the Facility Study phase. The Rockridge Solar Project has been mentioned in recent news coverage related to industry and deals.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Guadalupe
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Magnolia Solar Development LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7225 Hickory Forest 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Hickory Forest Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Rockridge Solar
Data-driven briefing on Rockridge Solar — fleet, generation, financial, and news signals.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Magnolia Solar
Data-driven briefing on Magnolia Solar — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.