Picadillo BESS
100.83 MW storage in Martin, TX · In queue since March 2022 · Proposed COD May 2028
100.83 MW
Capacity
1
Components
Battery
4y 8m
In Queue
IA Executed
IA Phase
Signed Jan 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 10m
IA → COD
4y 4m
Total Duration
1y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-05-15
Projected COD moved
6 times
May 2024 → May 2028
Net change
+48 months
first report to latest
Capacity
101 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
ERCOT Standard Generation Interconnection Agreement executed
interchange.puc.texas.govProposed commercial operation date per ERCOT queue and PUC Texas generation table
ftp.puc.texas.govResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0275/picadillo-bess
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
- ercot.com/files/docs/2025/03/07/CapacityChangesbyFuelTypeCharts_February_2025.xlsx
- ercot.com/files/docs/2026/02/05/Capacity-Changes-by-Fuel-Type-Charts_January_2026.xlsx
Commercial operation date: LBNL queue snapshot shows proposed COD of 2028-05-15, confirmed by multiple third-party aggregators (Cleanview, ERCOT capacity charts, PUC Texas gentable). No contradictory news or press releases found.
Developer: LBNL filing entity 'Black Mountain Energy Storage II' appears to be the operating company name, not a shell LLC. No press releases or corporate announcements found to identify a different parent entity.
Status: LBNL shows IA executed on 2024-01-23 with active status. PUC Texas filings confirm interconnection agreement. No construction announcements or groundbreaking news found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Picadillo BESS project is a proposed 100.83 MW battery storage project located in Martin County, Texas. The developer is Black Mountain Energy Storage II. It is interconnected within the ERCOT region under queue ID ERCOT-24INR0275, with an interconnection queue entry date of March 7, 2022. The project's proposed commercial operation date is May 15, 2028.
The project's Interconnection Agreement (IA) has been executed as of January 23, 2024. The point of interconnection (POI) is the 23837 Buffalo 138kV substation. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Martin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Black Mountain Energy Storage II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
23837 Buffalo 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Buffalo Gap 2 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.