Bufflehead BESS
153.3 MW storage in Collin, TX · In queue since March 2022 · Proposed COD February 2027
153.3 MW
Capacity
1
Components
Battery
4y 8m
In Queue
IA Executed
IA Phase
Signed Apr 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 1m
IA → COD
2y 10m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2027-02-15
Projected COD moved
7 times
Apr 2024 → Feb 2027
Net change
+34 months
first report to latest
Capacity
201 → 154 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
- 2025-03·Boxcar Energy Storage, LLC / Black Mountain Energy Storage→esVoltaenergy-storage.news
Milestones in this assessment
Standard Generation Interconnection Agreement executed with Oncor Electric Delivery
interchange.puc.texas.govesVolta acquired 150MW/300MWh BESS from Black Mountain Energy Storage
energy-storage.newsResearch sources and reasoning (4 recorded sources)
high confidence at research time
- energy-storage.news/esvolta-acquires-300mwh-ercot-bess-from-black-mountain-energy-storage/
- records.wylietexas.gov/WebLink/DocView.aspx?id=1172242&dbid=0&repo=City-of-Wylie
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- ercot.com/files/docs/2025/11/06/Capacity-Changes-by-Fuel-Type-Charts_October_2025_PlannedMonthly.xlsx
Commercial operation date: LBNL queue shows 2027-02-15 COD. ERCOT capacity chart (Nov 2025) lists 2027 target. No press releases or news articles with updated developer-announced dates found.
Developer: LBNL filing entity is 'Boxcar Energy Storage, LLC'. City of Wylie planning documents (Sep 2024) explicitly state 'Black Mountain Energy Storage partnering with esVolta' for Bufflehead BESS. Energy-Storage.News (Mar 2025) reports esVolta acquired a 150MW/300MWh ERCOT BESS from Black Mountain Energy Storage, matching this project's capacity and location.
Status: LBNL shows IA executed 2024-04-10, status active. PUC Interchange filings confirm ongoing interconnection agreement amendments with Oncor. Acquisition by esVolta suggests continued development momentum.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Bufflehead BESS is a proposed 159.23 MW battery storage project in Collin County, Texas. Developed by Boxcar Energy Storage, LLC, the project is located within the ERCOT region and consists entirely of battery storage. It entered the ERCOT interconnection queue as queue ID ERCOT-24INR0274 on March 7, 2022, with a proposed commercial operation date of February 15, 2027.
The project's Interconnection Agreement (IA) was executed on April 10, 2024. The point of interconnection is the 2475 Lavon Switch 138kV. The Bufflehead BESS project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Collin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Boxcar Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
2475 Lavon Switch 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.