Zeissel Solar
451.52 MW generation in Knox, TX · In queue since February 2022 · Proposed COD June 2028
451.52 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Phase
Signed Feb 2024
Queue → IA
2 years
IA → COD
4y 4m
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-06-30
The Zeissel Solar project is a proposed 457.5 MW solar generation facility in Knox County, Texas. The project, developed by ZSS Power, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0258, with a queue entry date of February 28, 2022. The proposed commercial operation date is June 30, 2028.
The project's interconnection agreement was executed on February 24, 2024. The point of interconnection is the 60700 Gauss 345 KV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Knox
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ZSS Power, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#60094 Joule 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Gauss Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.