St. Gall Solar
207 MW generation in Pecos, TX · In queue since February 2022 · Proposed COD June 2026
207 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Facility Study
IA Phase
COD target: 2026
Total Duration
4y 4m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
The St. Gall Solar project is a proposed 207 MW solar generation facility in Pecos County, Texas. The project, developed by St. Gall Solar LLC, is located within the ERCOT region and entered the interconnection queue as ERCOT-24INR0233 on February 28, 2022. The proposed commercial operation date is June 1, 2026, and the project's interconnection status is currently in the Facility Study phase.
The St. Gall Solar project has been the subject of recent news coverage, with six articles appearing in industry and grid-related publications.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
St. Gall Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
38355 Leon Creek 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LEONLCPCT1_2
- POI Substation
- Leon Creek Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.