Eastbell Milam Solar II
150.6 MW generation in Milam, TX · In queue since March 2022 · Proposed COD November 2026
150.6 MW
Capacity
1
Components
Solar
4y 8m
In Queue
IA Executed
IA Phase
Signed Oct 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 7m
IA → COD
3y 1m
Total Duration
1y 7m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2026-11-01
Projected COD moved
10 times
Oct 2024 → Nov 2026
Net change
+25 months
first report to latest
Capacity
153 → 151 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Texas Comptroller determination issued for Cattlemen Solar Park II LLC project in Rosebud-Lott ISD
assets.comptroller.texas.govInterconnection Agreement executed with Oncor Electric Delivery Company
interchange.puc.texas.govResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/solar-farms/texas/24INR0208/eastbell-milam-solar-ii
- ercot.com/files/docs/2024/11/01/MORA_January2025.xlsx
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- assets.comptroller.texas.gov/ch313/1754/1754-rosebud-cattlemen-cert-CORRECTED.pdf
- ercotqueue.com/project/24INR0208
Commercial operation date: LBNL queue shows proposed COD of 2026-03-31. ERCOT capacity charts from 2024 list the project with a 2024 target, but no press releases or developer announcements confirm current timeline. Defaulting to LBNL filing date absent stronger contradictory evidence.
Developer: All sources consistently identify Cattlemen Solar Park II LLC as the developer. No parent company or operating entity identified in search results. This appears to be a project-specific LLC with no public disclosure of ultimate ownership.
Status: LBNL shows 'active' status with IA executed 2023-10-25. ERCOT monthly outlook and capacity documents from 2024 continue to list the project, confirming it remains in active development with no withdrawal signals.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Eastbell Milam Solar II is a proposed solar generation project located in Milam County, Texas, with a total capacity of 150.6 MW. The developer is Cattlemen Solar Park II LLC. The project is interconnected within the ERCOT region and carries the queue ID ERCOT-24INR0208. It entered the interconnection queue on March 7, 2022, and has a proposed commercial operation date of November 27, 2025.
The project's Interconnection Agreement (IA) has been executed as of October 25, 2023. The point of interconnection (POI) is the 345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cattlemen Solar Park II LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.