Two Forks BESS (ERCOT-24INR0198) — Project Summary

Queue ID
ERCOT-24INR0198
Capacity
309.8 MW
Technology
Battery
Status
active
Location
Cooke, TX
Region
ERCOT
Developer
Two Forks LLC
IA Status
IA Executed

Two Forks BESS

ERCOT-24INR0198BetaActiveBatteryERCOTLBNL + Live

309.8 MW storage in Cooke, TX · In queue since January 2022 · Proposed COD August 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

309.8 MW

Capacity

1

Components

Battery

4y 10m

In Queue

IA Executed

IA Phase

Signed May 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 4m

IA → COD

4y 3m

Total Duration

2y 4m

Construction75%
Queue EntryJan 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 3, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-08-01

Queue history
24INR0198 · 48 monthly ERCOT reports, Oct 2022 – Sep 2026

Projected COD moved

5 times

Dec 2024 → Aug 2028

Net change

+44 months

first report to latest

Capacity

300 → 310 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 28, 2022
Interconnection agreement signedMay 3, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Aug 1, 2028
From queue filing
Developer in saved assessment
Two Forks LLC
From queue filing
Status at research time
IA Executed
Active in the ERCOT queue with the interconnection agreement executed (LBNL IA date 2024-05-03). Quicksand Check reports 'Signed; security posted' for the 684 SPRING 138kV interconnection. No construction start has been announced.
Financing
Not recorded
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0198/two-forks-bess
  2. quicksandcheck.com/texas/cooke-county/
  3. interconnection.fyi/project/ercot-24inr0198

Commercial operation date: No news or press release gives a developer-backed COD. Cleanview lists 'Expected online 2028' and Quicksand Check lists 'Sep 2028', but both look derived from queue data and are consistent with the LBNL 2028-08-01 date, so there is no evidence of a different date.

Developer: Quicksand Check repeats 'Two Forks LLC' as the developer. No source names a parent or operating company, so the project-LLC name is the only available answer.

Status: LBNL shows IA Executed and an active status. Quicksand Check's 'Signed; security posted' agrees with that, and no source reports withdrawal, suspension or construction.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Two Forks BESS is a proposed 309.8 MW battery storage project in Cooke County, Texas. Developed by Two Forks LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-24INR0198. The project entered the interconnection queue on January 28, 2022, and has a proposed commercial operation date of June 30, 2027.

The project's Interconnection Agreement (IA) was executed on May 3, 2024. The point of interconnection (POI) is the 684 SPRING 138kV. The development has been mentioned in recent news coverage related to the electric grid.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Cooke

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Two Forks LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

684 SPRING 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-26