Two Forks BESS
309.8 MW storage in Cooke, TX · In queue since January 2022 · Proposed COD August 2028
309.8 MW
Capacity
1
Components
Battery
4y 10m
In Queue
IA Executed
IA Phase
Signed May 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 4m
IA → COD
4y 3m
Total Duration
2y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-08-01
Projected COD moved
5 times
Dec 2024 → Aug 2028
Net change
+44 months
first report to latest
Capacity
300 → 310 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0198/two-forks-bess
- quicksandcheck.com/texas/cooke-county/
- interconnection.fyi/project/ercot-24inr0198
Commercial operation date: No news or press release gives a developer-backed COD. Cleanview lists 'Expected online 2028' and Quicksand Check lists 'Sep 2028', but both look derived from queue data and are consistent with the LBNL 2028-08-01 date, so there is no evidence of a different date.
Developer: Quicksand Check repeats 'Two Forks LLC' as the developer. No source names a parent or operating company, so the project-LLC name is the only available answer.
Status: LBNL shows IA Executed and an active status. Quicksand Check's 'Signed; security posted' agrees with that, and no source reports withdrawal, suspension or construction.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Two Forks BESS is a proposed 309.8 MW battery storage project in Cooke County, Texas. Developed by Two Forks LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-24INR0198. The project entered the interconnection queue on January 28, 2022, and has a proposed commercial operation date of June 30, 2027.
The project's Interconnection Agreement (IA) was executed on May 3, 2024. The point of interconnection (POI) is the 684 SPRING 138kV. The development has been mentioned in recent news coverage related to the electric grid.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Cooke
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Two Forks LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
684 SPRING 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.