Tehuacana Creek Solar
505.43 MW hybrid in Navarro, TX · In queue since December 2021 · Proposed COD May 2027
505.43 MW
Capacity
1
Components
Solar
4y 11m
In Queue
IA Executed
IA Phase
Signed Nov 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 11m
IA → COD
2y 6m
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-05-18
Projected COD moved
7 times
Jun 2024 → May 2027
Net change
+35 months
first report to latest
Capacity
700 → 505 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (8 recorded sources)
medium confidence at research time
- renewablesnow.com/news/parliament-energy-secures-usd-747m-in-financing-for-texas-solar-project-1297143/
- pv-magazine-usa.com/2026/04/14/ideematec-to-supply-1-2-gw-of-trackers-for-texas-solar-portfolio/
- parliamentenergy.com/tehuacana-creek
- infrasure.ai/plant/65855-tehuacana-creek-1-solar-and-bess
- cleanview.co/power-projects/planned/solar-farms/texas/65855_TE1PV/tehuacana-creek-solar
- cleanview.co/power-projects/planned/battery-storage-projects/texas/65855_TE1BS/tehuacana-creek-solar
- gem.wiki/Tehuacana_Creek_Solar
- msn.com/en-us/money/markets/one-texas-project-tehuacana-creek-1-is-2026-s-biggest-us-solar-build-at-837-mw-plus-418-mw-of-co-located-battery-storage/ar-AA24PFkp
Commercial operation date: Cleanview lists the solar component as 'Expected online 2027', which matches the LBNL proposed COD of 2027-05-18. The battery is listed for 2026, and an MSN headline calls the project one of 2026's biggest builds, so some phasing may come earlier. No source gives a firm date that contradicts LBNL by 1 year or more.
Developer: Parliament Energy's own project page presents Tehuacana Creek (650 MWdc / 505 MWac, Navarro and Freestone counties) as its project. Infrasure lists the operator as Parliament Energy Holdings LLC, so the LBNL LLC is the project shell. Parliament was established by EnCap Energy Transition Fund II and Mercuria.
Status: The LBNL queue state is Active with an executed IA. Later sources (EIA 860M via Infrasure, a financing close, tracker procurement) point to construction, with only the earlier GEM entry saying pre-construction.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Tehuacana Creek Solar SLF project is a proposed 505.5 MW solar generation project located in Navarro County, Texas. It is listed in the ERCOT interconnection queue as entry ERCOT-24INR0188, with a queue entry date of December 20, 2021. The proposed commercial operation date is March 10, 2027.
The project has an Interconnection Agreement (IA) date of November 25, 2024. The developer is not specified in the available data. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tehuacana Creek Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3381 Big Brown – 68091 Navarro circuit
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.