Rowdy Creek BESS
175.89 MW generation in Lamar, TX · In queue since January 2022 · Proposed COD April 2027
175.89 MW
Capacity
1
Components
Battery
4y 10m
In Queue
IA Executed
IA Phase
Signed May 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 4m
IA → COD
1y 11m
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-04-01
Projected COD moved
4 times
Jun 2024 → Apr 2027
Net change
+34 months
first report to latest
Capacity
350 → 176 MW
changed in the reports
Latest stage
Cancelled
last listed Feb 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with Oncor Electric Delivery Company
interchange.puc.texas.govERCOT capacity planning documents list 2027 commercial operation target
ercot.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- aterio.io/insights/us-energy-projects/ep/rowdy-creek-project
- interconnection.fyi/project/ercot-24inr0187
- ercot.com/files/docs/2025/12/04/Capacity-Changes-by-Fuel-Type-Charts_November_2025_PlannedMonthly.xlsx
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
Commercial operation date: LBNL queue snapshot shows proposed COD of 2027-04-01, confirmed by ERCOT's December 2025 capacity planning spreadsheet listing 2027 target. No contradicting news sources found.
Developer: LBNL filing entity 'Rowdy Creek Solar LLC' appears to be the actual project developer rather than a shell LLC. Texas PUC filings consistently reference this entity as the project owner with no parent company identified in available sources.
Status: LBNL shows 'active' status with IA executed on 2025-05-02. However, interconnection.fyi database indicates project status as 'withdrawn', creating conflicting signals. LBNL IA execution date is more recent (May 2025) and authoritative.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Rowdy Creek BESS is a proposed battery storage project located in Lamar County, Texas, with a total capacity of 175.89 MW. The project, developed by Rowdy Creek Solar LLC, is currently in the ERCOT interconnection queue as entry ERCOT-24INR0187, with a queue entry date of January 28, 2022. Its proposed commercial operation date is April 1, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists entirely of battery storage. The point of interconnection is Tap 345kV 1692 Paris Switch _x0013_ 1690 Valley SES. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Feb 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rowdy Creek Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1692 Paris Switch – 1690 Valley SES
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.